Home
Class 14
MATHS
Colonel, Major and General started a wor...

Colonel, Major and General started a work together for Rs. 816. Colonel and Major did `(8)/(17)` of the total work, while Major and General together did `(12)/(17)`of the whole work. What is the amount of the least efficient person?

A

Rs. 256

B

Rs. 144

C

Rs. 85

D

can't be determined.

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to find the amount earned by the least efficient person among Colonel, Major, and General based on the work they did together. ### Step 1: Understand the Work Distribution We know that: - Colonel and Major together did \( \frac{8}{17} \) of the total work. - Major and General together did \( \frac{12}{17} \) of the total work. Let the total work be represented as 17 units (for simplicity). ### Step 2: Calculate Work Done by Colonel and Major If the total work is 17 units, then the work done by Colonel and Major together is: \[ C + M = \frac{8}{17} \times 17 = 8 \text{ units} \] ### Step 3: Calculate Work Done by Major and General Similarly, the work done by Major and General together is: \[ M + G = \frac{12}{17} \times 17 = 12 \text{ units} \] ### Step 4: Set Up the Equations Now we have two equations: 1. \( C + M = 8 \) (Equation 1) 2. \( M + G = 12 \) (Equation 2) ### Step 5: Solve for General's Work From Equation 1, we can express Colonel's work in terms of Major's work: \[ C = 8 - M \quad \text{(Equation 3)} \] Substituting Equation 3 into Equation 2: \[ M + G = 12 \implies G = 12 - M \quad \text{(Equation 4)} \] ### Step 6: Find Work Done by Each Person Now we have: - Colonel's work: \( C = 8 - M \) - Major's work: \( M \) - General's work: \( G = 12 - M \) ### Step 7: Find the Value of M To find the individual work done by each person, we can add the total work done: \[ C + M + G = 17 \] Substituting the values from Equations 3 and 4: \[ (8 - M) + M + (12 - M) = 17 \] Simplifying: \[ 8 + 12 - M = 17 \implies 20 - M = 17 \implies M = 3 \] ### Step 8: Calculate Work Done by Colonel and General Now substituting \( M = 3 \) back into Equations 3 and 4: - Colonel's work: \[ C = 8 - 3 = 5 \] - General's work: \[ G = 12 - 3 = 9 \] ### Step 9: Identify the Least Efficient Person The work done by each person is: - Colonel: 5 units - Major: 3 units - General: 9 units The least efficient person is Major, who did 3 units of work. ### Step 10: Calculate the Amount Earned by the Least Efficient Person The total payment for the work is Rs. 816. The amount earned by each unit of work is: \[ \text{Amount per unit} = \frac{816}{17} = 48 \] Thus, the amount earned by Major (least efficient person) is: \[ \text{Amount for Major} = 3 \text{ units} \times 48 = 144 \] ### Final Answer The amount earned by the least efficient person (Major) is Rs. 144. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

Colonel, Major and General started a work together fort ₹ 816. Colonel and Major did 8/17 of the total work, while Major and General together did (12/17) of the whole work. What is the amount of the least efficient person?

If A takes 4//5 days as B-takes and working together they require (20)/3 days to complete the whole work. What is the efficiency of B ?

P, Q and R undertook a work for Rs 55000. Together P and Q complete (8//11)^(th) part of the work. What is the share (in Rs) of R?

Anand can do a piece of work in 45 days, but Bahuguna can do the same work in 5 days less, than Anand, when working alone. Anand and Bahuguna both started the work together but Bahuguna left after some days and Anand finished the remaining work in 56 days with half of his efficiency but he did the work with Bahuguna with his complete efficiency. For how many days they had worked together?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. C takes twice the number of days to do a piece of work than A takes. A...

    Text Solution

    |

  2. When A, B and Care deployed for a task, A and B together do 70% of the...

    Text Solution

    |

  3. Colonel, Major and General started a work together for Rs. 816. Colone...

    Text Solution

    |

  4. Sharma is 20% less efficient than Kelkar. If Kelkar can do a piece of ...

    Text Solution

    |

  5. 30 persons can do a piece of work in 24 days. How many more people are...

    Text Solution

    |

  6. 12 women can do a piece of work in 20 days. If the 4 women deny to wor...

    Text Solution

    |

  7. 35 boys can do a piece of work in 15 days. The work will completed in ...

    Text Solution

    |

  8. 24 men can complete a job in 40 days. The number men required to compl...

    Text Solution

    |

  9. 16 men finished one-third work in 6 days. The number of additional men...

    Text Solution

    |

  10. If 10 persons can do a job in 20 days, then 20 person with twice the e...

    Text Solution

    |

  11. A certain job was assigned to a group of men to do in 20 days. But 12 ...

    Text Solution

    |

  12. 30 workers can finish a work in 20 days. After how many days should 9 ...

    Text Solution

    |

  13. 25 men can complete a job in 30 days. After how many days should the s...

    Text Solution

    |

  14. A group of workers can complete a job in 120 days. If there were 4 mor...

    Text Solution

    |

  15. Mr. Modi can copy 40 pages in 10 minutes, Mr Xerox and Mr. Modi both w...

    Text Solution

    |

  16. 20 persons completed (1)/(3)rd of the work in 24 days. How many more p...

    Text Solution

    |

  17. A contractor undertook a work to complete in 60 days. But just after 2...

    Text Solution

    |

  18. 6 men or 10 women can reap a field in 15 days, then the number of days...

    Text Solution

    |

  19. If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then ...

    Text Solution

    |

  20. 2 men or 5 women or 7 boys can finish a work in 469 days. then the num...

    Text Solution

    |