30 persons can do a piece of work in 24 ...

30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?

A

4

B

5

C

6

D

none of these

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will use the relationship between the number of workers, the number of days, and the amount of work done. ### Step 1: Understand the given data We know that: - 30 persons can complete the work in 24 days. ### Step 2: Calculate the total work in terms of person-days Total work can be calculated as: \[ \text{Total Work} = \text{Number of Persons} \times \text{Number of Days} \] So, in this case: \[ \text{Total Work} = 30 \text{ persons} \times 24 \text{ days} = 720 \text{ person-days} \] ### Step 3: Determine the number of persons required to complete the work in 20 days Let \( M_2 \) be the number of persons required to complete the same work in 20 days. We can set up the equation: \[ M_2 \times 20 \text{ days} = 720 \text{ person-days} \] To find \( M_2 \), we rearrange the equation: \[ M_2 = \frac{720 \text{ person-days}}{20 \text{ days}} = 36 \text{ persons} \] ### Step 4: Calculate how many more persons are needed We need to find out how many more persons are required compared to the original 30 persons: \[ \text{More persons required} = M_2 - M_1 = 36 - 30 = 6 \] ### Final Answer Thus, the number of additional persons required to complete the work in 20 days is **6 persons**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

15 persons can do a piece of work in 12 days. How many more people are required to complete the work in 10 days?

If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.

If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:

Twelve persons can do a piece of work in 20 days. How many persons are required to do the same in 24 days?

If 20 persons can do a piece of work in 7 days then calculate the number of persons required to complete the work in 28 days

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. Colonel, Major and General started a work together for Rs. 816. Colone...

    Text Solution

    |

  2. Sharma is 20% less efficient than Kelkar. If Kelkar can do a piece of ...

    Text Solution

    |

  3. 30 persons can do a piece of work in 24 days. How many more people are...

    Text Solution

    |

  4. 12 women can do a piece of work in 20 days. If the 4 women deny to wor...

    Text Solution

    |

  5. 35 boys can do a piece of work in 15 days. The work will completed in ...

    Text Solution

    |

  6. 24 men can complete a job in 40 days. The number men required to compl...

    Text Solution

    |

  7. 16 men finished one-third work in 6 days. The number of additional men...

    Text Solution

    |

  8. If 10 persons can do a job in 20 days, then 20 person with twice the e...

    Text Solution

    |

  9. A certain job was assigned to a group of men to do in 20 days. But 12 ...

    Text Solution

    |

  10. 30 workers can finish a work in 20 days. After how many days should 9 ...

    Text Solution

    |

  11. 25 men can complete a job in 30 days. After how many days should the s...

    Text Solution

    |

  12. A group of workers can complete a job in 120 days. If there were 4 mor...

    Text Solution

    |

  13. Mr. Modi can copy 40 pages in 10 minutes, Mr Xerox and Mr. Modi both w...

    Text Solution

    |

  14. 20 persons completed (1)/(3)rd of the work in 24 days. How many more p...

    Text Solution

    |

  15. A contractor undertook a work to complete in 60 days. But just after 2...

    Text Solution

    |

  16. 6 men or 10 women can reap a field in 15 days, then the number of days...

    Text Solution

    |

  17. If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then ...

    Text Solution

    |

  18. 2 men or 5 women or 7 boys can finish a work in 469 days. then the num...

    Text Solution

    |

  19. 6 children and 2 men complete a certain piece of work in 6 days. Each ...

    Text Solution

    |

  20. 2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14...

    Text Solution

    |