2 men and 3 women finish 25% of the work...

2 men and 3 women finish `25%` of the work in 4 days, while 6 men and 14 women can finish the whole work in 5 days. In how many days will 20 women finish it?

A

20

B

25

C

24

D

88

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Understand the Work Done We know that 2 men and 3 women finish 25% of the work in 4 days. Therefore, if 25% of the work is done in 4 days, then 100% of the work will take: \[ \text{Total days for 100% work} = 4 \text{ days} \times 4 = 16 \text{ days} \]
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

If 40 men can finish a piece of work in 60 days. In how many days will 75 , men finish the same work ?

4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish in 10 days. In how many days will 10 women finish it?

7 men can complete a work in 52 days. In how many days will 13 men finish the same work.

4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?

4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 boys can finish the same work in 5 days. Also 2 men and 3 women can finish the same work in 5 days. In how many days 1 man, 1 woman and one boy can finish the work, at their double efficiency?

30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?

4men and 6 women can complete a work in 8 days,While 3 men and 7 women can complete it in 10 days.In how many days will 10 women complete it.

When 6 men and 8 women can do a piece of work in 15 days, then 11 men and 16 women can do the same work in 8 days. In how many days can 4 men and 4 women do the work ?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. 2 men or 5 women or 7 boys can finish a work in 469 days. then the num...

    Text Solution

    |

  2. 6 children and 2 men complete a certain piece of work in 6 days. Each ...

    Text Solution

    |

  3. 2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14...

    Text Solution

    |

  4. How long will it take C to finish the work alone?

    Text Solution

    |

  5. The ratio of efficiencies of A,B and C is 6:5:4 and if A, B and C rece...

    Text Solution

    |

  6. 314 weavers weaves 6594 shawls in (1)/(6) hours. What is the number of...

    Text Solution

    |

  7. Three men and two women can do a piece of work in 4 days, while two me...

    Text Solution

    |

  8. 30 girls can finish a work in 40 days. After how many days should 10 g...

    Text Solution

    |

  9. If 8 women collect 200 kg of tea leaves in 10 hours. How many more (in...

    Text Solution

    |

  10. 450 man-days of work can be completed by a certain number of men in so...

    Text Solution

    |

  11. 4 boys and 5 girls can do a piece of work in 10 days. 6 boys and 6 gir...

    Text Solution

    |

  12. If 20 engineers and 20 workers can together construct a 20 km road in ...

    Text Solution

    |

  13. (x - 2) men can do a piece of work in x days and (x + 7) men can do 75...

    Text Solution

    |

  14. A man, a woman and a girl worked for a contractor for the same period....

    Text Solution

    |

  15. 33 men can do a job in 30 days. If 44 men started the job together and...

    Text Solution

    |

  16. Abhishek can do a piece of work in 40 days. He alone worked at it for ...

    Text Solution

    |

  17. C is twice efficient as A. B takes thrice as many days as C. A takes 1...

    Text Solution

    |

  18. Ahluwalia and Bimal together take 6 days to finish the work. Bimal and...

    Text Solution

    |

  19. B is twice efficient as A and A can do a piece of work in 15 days. A s...

    Text Solution

    |

  20. A, B and C can complete a piece of work in 15, 30 and 40 days respecti...

    Text Solution

    |