Home
Class 14
MATHS
(x - 2) men can do a piece of work in x ...

`(x - 2)` men can do a piece of work in x days and `(x + 7)` men can do `75%` of the same work in `(x - 10)` days. Then in how many days can `(x + 10)` men finish the work?

A

27 days

B

12 days

C

25 days

D

18 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these steps: ### Step 1: Set up the equations based on the information given. We know that `(x - 2)` men can do a piece of work in `x` days. Therefore, the total work (W) can be expressed as: \[ W = (x - 2) \times x \] ### Step 2: Express the work done by `(x + 7)` men in `(x - 10)` days. According to the problem, `(x + 7)` men can do `75%` of the same work in `(x - 10)` days. Thus, the work done by `(x + 7)` men can be expressed as: \[ W_{75\%} = (x + 7) \times (x - 10) \] Since this is `75%` of the total work, we can write: \[ W_{75\%} = 0.75 \times W = 0.75 \times (x - 2) \times x \] ### Step 3: Set the two expressions for work equal to each other. Now we can set the two expressions for work equal to each other: \[ (x + 7)(x - 10) = 0.75 \times (x - 2) \times x \] ### Step 4: Expand both sides of the equation. Expanding the left side: \[ (x + 7)(x - 10) = x^2 - 10x + 7x - 70 = x^2 - 3x - 70 \] Expanding the right side: \[ 0.75 \times (x - 2) \times x = 0.75(x^2 - 2x) = 0.75x^2 - 1.5x \] ### Step 5: Set the equation to zero. Now we can set the equation: \[ x^2 - 3x - 70 = 0.75x^2 - 1.5x \] Rearranging gives: \[ x^2 - 0.75x^2 - 3x + 1.5x - 70 = 0 \] \[ 0.25x^2 - 1.5x - 70 = 0 \] ### Step 6: Multiply through by 4 to eliminate the decimal. Multiplying the entire equation by 4: \[ x^2 - 6x - 280 = 0 \] ### Step 7: Factor the quadratic equation. We can factor the quadratic: \[ (x - 20)(x + 14) = 0 \] ### Step 8: Solve for x. Setting each factor to zero gives: 1. \( x - 20 = 0 \) → \( x = 20 \) 2. \( x + 14 = 0 \) → \( x = -14 \) (not valid since x must be positive) Thus, \( x = 20 \). ### Step 9: Find the number of men. Now, we need to find the number of men when \( x + 10 \): \[ x + 10 = 20 + 10 = 30 \text{ men} \] ### Step 10: Calculate the total work. Using the total work formula: \[ W = (x - 2) \times x = (20 - 2) \times 20 = 18 \times 20 = 360 \text{ units} \] ### Step 11: Calculate the number of days for 30 men to finish the work. Using the formula for the time taken: \[ \text{Days} = \frac{\text{Total Work}}{\text{Number of Men}} = \frac{360}{30} = 12 \text{ days} \] ### Final Answer: Thus, `(x + 10)` men can finish the work in **12 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the same work ?

If 52 men can do a piece of work in 35 days in how many days 28 men will do it?

If 4 men or 7 women can do a work in 60 days, then in how many days will 8 men and 7 women finish the same work?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. 4 boys and 5 girls can do a piece of work in 10 days. 6 boys and 6 gir...

    Text Solution

    |

  2. If 20 engineers and 20 workers can together construct a 20 km road in ...

    Text Solution

    |

  3. (x - 2) men can do a piece of work in x days and (x + 7) men can do 75...

    Text Solution

    |

  4. A man, a woman and a girl worked for a contractor for the same period....

    Text Solution

    |

  5. 33 men can do a job in 30 days. If 44 men started the job together and...

    Text Solution

    |

  6. Abhishek can do a piece of work in 40 days. He alone worked at it for ...

    Text Solution

    |

  7. C is twice efficient as A. B takes thrice as many days as C. A takes 1...

    Text Solution

    |

  8. Ahluwalia and Bimal together take 6 days to finish the work. Bimal and...

    Text Solution

    |

  9. B is twice efficient as A and A can do a piece of work in 15 days. A s...

    Text Solution

    |

  10. A, B and C can complete a piece of work in 15, 30 and 40 days respecti...

    Text Solution

    |

  11. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  12. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |

  13. 7 Indian and 4 Chinese finish a job in 5 days. 7 Japanese and 3 Chines...

    Text Solution

    |

  14. A, B and C are three book binders. A takes 8 minutes, B takes 12 minut...

    Text Solution

    |

  15. A piece of work can be completed by 10 men and 6 women in 18 days. Men...

    Text Solution

    |

  16. B and C are equally efficient, but the efficiency of A is half of each...

    Text Solution

    |

  17. A can do a piece of work in 10 days, B in 15 days. They work together ...

    Text Solution

    |

  18. A can do a piece of work in 2 hours, B can do thrice the work in 8 hou...

    Text Solution

    |

  19. A is twice efficient as B and together they do the same work in as muc...

    Text Solution

    |

  20. 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 b...

    Text Solution

    |