Abhishek can do a piece of work in 40 da...

Abhishek can do a piece of work in 40 days. He alone worked at it for 8 days and then Bacchhan completed alone the rest work in 24 days. In how many days they will complete the whole work, working together ?

A

`17(1)/(7)` days

B

`18(1)/(17)` days

C

`9(1)/(6)` days

D

`14 days`

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

A can do a piece of work in 8 days, B can do it in 16 days, while C can do it in 80 days. In how many days they can complete the whole work, working together?

A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?

A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?

Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?

If Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. A man, a woman and a girl worked for a contractor for the same period....

    Text Solution

    |

  2. 33 men can do a job in 30 days. If 44 men started the job together and...

    Text Solution

    |

  3. Abhishek can do a piece of work in 40 days. He alone worked at it for ...

    Text Solution

    |

  4. C is twice efficient as A. B takes thrice as many days as C. A takes 1...

    Text Solution

    |

  5. Ahluwalia and Bimal together take 6 days to finish the work. Bimal and...

    Text Solution

    |

  6. B is twice efficient as A and A can do a piece of work in 15 days. A s...

    Text Solution

    |

  7. A, B and C can complete a piece of work in 15, 30 and 40 days respecti...

    Text Solution

    |

  8. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  9. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |

  10. 7 Indian and 4 Chinese finish a job in 5 days. 7 Japanese and 3 Chines...

    Text Solution

    |

  11. A, B and C are three book binders. A takes 8 minutes, B takes 12 minut...

    Text Solution

    |

  12. A piece of work can be completed by 10 men and 6 women in 18 days. Men...

    Text Solution

    |

  13. B and C are equally efficient, but the efficiency of A is half of each...

    Text Solution

    |

  14. A can do a piece of work in 10 days, B in 15 days. They work together ...

    Text Solution

    |

  15. A can do a piece of work in 2 hours, B can do thrice the work in 8 hou...

    Text Solution

    |

  16. A is twice efficient as B and together they do the same work in as muc...

    Text Solution

    |

  17. 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 b...

    Text Solution

    |

  18. If m men can do a work in r days, then the number of days taken by (m+...

    Text Solution

    |

  19. Pipe A can fill a tank in 36 minutes and pipe B can fill it in 45 minu...

    Text Solution

    |

  20. Tap A can fill the empty tank in 12 hours, but due to a leak in the bo...

    Text Solution

    |