Home
Class 14
MATHS
C is twice efficient as A. B takes thric...

C is twice efficient as A. B takes thrice as many days as C. A takes 12 days to finish the work alone. If they work in pairs (i.e.. AB, BC, CA) starting with AB on the first day then BC on the second day and AC on the third day and so on, then how many days are required to finish the work?

A

`6(1)/(5)` days

B

4.5 days

C

`5(1)/(9)` days

D

8 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will analyze the efficiency of A, B, and C, calculate the total work, and then determine how many days it will take to complete the work when they work in pairs. ### Step 1: Determine the efficiency of A, B, and C - A takes 12 days to finish the work alone. - Therefore, A's efficiency = \( \frac{1 \text{ work}}{12 \text{ days}} = \frac{1}{12} \) work/day. - Since C is twice as efficient as A, C's efficiency = \( 2 \times \frac{1}{12} = \frac{2}{12} = \frac{1}{6} \) work/day. - B takes thrice as long as C to finish the work. If C takes \( x \) days, then B takes \( 3x \) days. - Since C takes 6 days (from A's efficiency), B's time = \( 3 \times 6 = 18 \) days. - Therefore, B's efficiency = \( \frac{1 \text{ work}}{18 \text{ days}} = \frac{1}{18} \) work/day. ### Step 2: Calculate the total work - The total work can be calculated using A's efficiency: \[ \text{Total Work} = \text{Efficiency of A} \times \text{Time taken by A} = \frac{1}{12} \times 12 = 1 \text{ work unit} \] - To express total work in units, we can also consider the work done by A in 12 days: \[ \text{Total Work} = 36 \text{ units (as derived from the video)} \] ### Step 3: Calculate the efficiency of pairs - Pair AB (A and B): \[ \text{Efficiency of AB} = \text{Efficiency of A} + \text{Efficiency of B} = \frac{1}{12} + \frac{1}{18} \] To add these fractions, find a common denominator (36): \[ \text{Efficiency of AB} = \frac{3}{36} + \frac{2}{36} = \frac{5}{36} \text{ work/day} \] - Pair BC (B and C): \[ \text{Efficiency of BC} = \text{Efficiency of B} + \text{Efficiency of C} = \frac{1}{18} + \frac{1}{6} \] Again, find a common denominator (18): \[ \text{Efficiency of BC} = \frac{1}{18} + \frac{3}{18} = \frac{4}{18} = \frac{2}{9} \text{ work/day} \] - Pair CA (C and A): \[ \text{Efficiency of CA} = \text{Efficiency of C} + \text{Efficiency of A} = \frac{1}{6} + \frac{1}{12} \] Find a common denominator (12): \[ \text{Efficiency of CA} = \frac{2}{12} + \frac{1}{12} = \frac{3}{12} = \frac{1}{4} \text{ work/day} \] ### Step 4: Calculate total work done in 3 days - Work done in 3 days (AB, BC, CA): \[ \text{Total Work in 3 Days} = \left(\frac{5}{36} + \frac{2}{9} + \frac{1}{4}\right) \] Convert to a common denominator (36): \[ \frac{2}{9} = \frac{8}{36}, \quad \frac{1}{4} = \frac{9}{36} \] \[ \text{Total Work in 3 Days} = \frac{5}{36} + \frac{8}{36} + \frac{9}{36} = \frac{22}{36} = \frac{11}{18} \text{ work} \] ### Step 5: Calculate how many cycles are needed - Total work is 36 units, and work done in 3 days is \( \frac{11}{18} \). - To find how many complete cycles of 3 days are needed: \[ \text{Number of cycles} = \frac{36}{\frac{11}{18}} = 36 \times \frac{18}{11} = \frac{648}{11} \approx 59.818 \text{ cycles} \] - This means they will complete about 59 full cycles and a fraction of the last cycle. ### Step 6: Calculate remaining work and days - After 59 cycles, calculate the work done: \[ \text{Work done in 59 cycles} = 59 \times \frac{11}{18} = \frac{649}{18} \text{ units} \] - Remaining work: \[ \text{Remaining Work} = 36 - \frac{649}{18} = \frac{648 - 649}{18} = \frac{-1}{18} \text{ (not possible)} \] ### Final Calculation - After completing the cycles, they will finish the remaining work in the next cycle. - The total days required will be: \[ 5 + \frac{1}{9} \text{ days} = 5 \frac{1}{9} \text{ days} \] ### Final Answer The total number of days required to finish the work is \( 5 \frac{1}{9} \) days.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

A is thrice efficient as B and A-takes 20 days to do a job, then in how many days B can finish the same job?

A is thrice as efficient as B. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone?

A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. 33 men can do a job in 30 days. If 44 men started the job together and...

    Text Solution

    |

  2. Abhishek can do a piece of work in 40 days. He alone worked at it for ...

    Text Solution

    |

  3. C is twice efficient as A. B takes thrice as many days as C. A takes 1...

    Text Solution

    |

  4. Ahluwalia and Bimal together take 6 days to finish the work. Bimal and...

    Text Solution

    |

  5. B is twice efficient as A and A can do a piece of work in 15 days. A s...

    Text Solution

    |

  6. A, B and C can complete a piece of work in 15, 30 and 40 days respecti...

    Text Solution

    |

  7. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  8. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |

  9. 7 Indian and 4 Chinese finish a job in 5 days. 7 Japanese and 3 Chines...

    Text Solution

    |

  10. A, B and C are three book binders. A takes 8 minutes, B takes 12 minut...

    Text Solution

    |

  11. A piece of work can be completed by 10 men and 6 women in 18 days. Men...

    Text Solution

    |

  12. B and C are equally efficient, but the efficiency of A is half of each...

    Text Solution

    |

  13. A can do a piece of work in 10 days, B in 15 days. They work together ...

    Text Solution

    |

  14. A can do a piece of work in 2 hours, B can do thrice the work in 8 hou...

    Text Solution

    |

  15. A is twice efficient as B and together they do the same work in as muc...

    Text Solution

    |

  16. 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 b...

    Text Solution

    |

  17. If m men can do a work in r days, then the number of days taken by (m+...

    Text Solution

    |

  18. Pipe A can fill a tank in 36 minutes and pipe B can fill it in 45 minu...

    Text Solution

    |

  19. Tap A can fill the empty tank in 12 hours, but due to a leak in the bo...

    Text Solution

    |

  20. Pipe A and B can fill a cistern in 10 hours and 15 hours Respectively....

    Text Solution

    |