Home
Class 14
MATHS
A contractor undertook to complete the w...

A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that `(1)/(3)rd` of the work was still to be done. How many more men were required to complete the work in stipulated time?

A

16

B

15

C

20

D

25

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the reasoning provided in the video transcript. ### Step 1: Understand the total work and initial conditions The contractor has 40 days to complete the work and has deployed 20 men. ### Step 2: Calculate the total work done in 32 days Since he realized 8 days before the scheduled time that 1/3 of the work was still to be done, it means he completed 2/3 of the work in the first 32 days. ### Step 3: Determine the amount of work done by 20 men in 32 days Let the total work be represented as W. The work done in 32 days by 20 men can be calculated as: \[ \text{Work done} = \text{Number of men} \times \text{Days} = 20 \text{ men} \times 32 \text{ days} \] This means: \[ \frac{2}{3} W = 20 \times 32 \] \[ \frac{2}{3} W = 640 \] To find W, we can rearrange the equation: \[ W = 640 \times \frac{3}{2} = 960 \] ### Step 4: Calculate the remaining work Since 1/3 of the work is still to be done, we can calculate: \[ \text{Remaining work} = \frac{1}{3} W = \frac{1}{3} \times 960 = 320 \] ### Step 5: Determine the remaining time There are 8 days left to complete the remaining work. ### Step 6: Calculate the number of men needed to complete the remaining work Let X be the number of additional men required. The total number of men working now will be \( 20 + X \). The work done by these men in 8 days should equal the remaining work: \[ (20 + X) \times 8 = 320 \] ### Step 7: Solve for X Now we can solve the equation: \[ 20 \times 8 + X \times 8 = 320 \] \[ 160 + 8X = 320 \] Subtracting 160 from both sides gives: \[ 8X = 160 \] Dividing both sides by 8 gives: \[ X = 20 \] ### Conclusion The contractor needs to hire 20 more men to complete the work on time.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

10 men can make a wall in 8 days. How many men required to complete the same work in half day

20 men can do a work in 35 days. How many men are needed to complete the same work in 25 days.

Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?

A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. A, B and C can complete a piece of work in 15, 30 and 40 days respecti...

    Text Solution

    |

  2. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  3. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |

  4. 7 Indian and 4 Chinese finish a job in 5 days. 7 Japanese and 3 Chines...

    Text Solution

    |

  5. A, B and C are three book binders. A takes 8 minutes, B takes 12 minut...

    Text Solution

    |

  6. A piece of work can be completed by 10 men and 6 women in 18 days. Men...

    Text Solution

    |

  7. B and C are equally efficient, but the efficiency of A is half of each...

    Text Solution

    |

  8. A can do a piece of work in 10 days, B in 15 days. They work together ...

    Text Solution

    |

  9. A can do a piece of work in 2 hours, B can do thrice the work in 8 hou...

    Text Solution

    |

  10. A is twice efficient as B and together they do the same work in as muc...

    Text Solution

    |

  11. 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 b...

    Text Solution

    |

  12. If m men can do a work in r days, then the number of days taken by (m+...

    Text Solution

    |

  13. Pipe A can fill a tank in 36 minutes and pipe B can fill it in 45 minu...

    Text Solution

    |

  14. Tap A can fill the empty tank in 12 hours, but due to a leak in the bo...

    Text Solution

    |

  15. Pipe A and B can fill a cistern in 10 hours and 15 hours Respectively....

    Text Solution

    |

  16. A cistern has a leak which would empty it in 6 hours. A tap is turned ...

    Text Solution

    |

  17. Tap a fills a tank in 10 hours and B can fill it in 15 hours. Both are...

    Text Solution

    |

  18. Tap A can fill a tank in 20 hours, B in 25 hours but tap C can empty a...

    Text Solution

    |

  19. If one pipe A can fill a tank in 20 minutes, then 5 pipes, each of 20%...

    Text Solution

    |

  20. Pipe A basically used as inlet pipe and pipe B is used as outlet pipe....

    Text Solution

    |