A and B can complete the work individual...

A and B can complete the work individually in 24 days and 30 days respectively, working 10 hours a day. Work is to be done in two shift. Morning shift lasts for 6 hours and evening shift lasts for 4 hours. On the first day A works in the morning shift while B works in the evening shift. Next day A works in the evening shift while B works in the morning shift and so on. It means they work alternatively with respect to their shifts. Thus they work on this pattern till the work is completed. On which day the work got completed?

A

26th

B

17th

C

28th

D

30th

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 1)|100 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

A and B can do a work in 20 days and 30 days respectively. A and B work on alternate days. Find the number of days to complete the work

12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a day?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 2)
  1. Arun and Satyam can complete a work individually in ,12 working days a...

    Text Solution

    |

  2. Kaushalya can do a work in 20 days, while Kaikeyi can do the same work...

    Text Solution

    |

  3. A and B can complete the work individually in 24 days and 30 days resp...

    Text Solution

    |

  4. In the previous question what per cent of the time of the morning shif...

    Text Solution

    |

  5. Working together B and C take 50% more number of days than A,B and C t...

    Text Solution

    |

  6. At Technosys Pvt Ltd. there are some engineering students employed as ...

    Text Solution

    |

  7. At Atharva Prakashan every book goes through 3 phases – typing, compos...

    Text Solution

    |

  8. If 12 men or 20 women can do a work in 54 days, then in how many days ...

    Text Solution

    |

  9. In the given pie-chart. what is the number of employees working in dep...

    Text Solution

    |

  10. Bunty and Babli working together completed a job in 8 days. If Bunty w...

    Text Solution

    |

  11. A single reservoir supplies the petrol to the whole city, while the re...

    Text Solution

    |

  12. In question 118, if m(1) and m(2) are the magnifications for two posit...

    Text Solution

    |

  13. A Contractor employed a certain number of workers to finish construct...

    Text Solution

    |

  14. Some-time after the new workers were introduced, all of the newly intr...

    Text Solution

    |

  15. Mr. stenley employed a certain number of typist for his project. 8 day...

    Text Solution

    |

  16. Mr. stenley employed a certain number of typist for his project. 8 day...

    Text Solution

    |

  17. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  18. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  19. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  20. Five tailors A, B, C, D and E stich 1800 shirts in 90 days working alt...

    Text Solution

    |