A Contractor employed a certain number o...

A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?

A

a. `10%`

B

b. `14(2)/(7)%`

C

c. `20%`

D

d. can't be determined

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 1)|100 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time

A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 2)
  1. A single reservoir supplies the petrol to the whole city, while the re...

    Text Solution

    |

  2. In question 118, if m(1) and m(2) are the magnifications for two posit...

    Text Solution

    |

  3. A Contractor employed a certain number of workers to finish construct...

    Text Solution

    |

  4. Some-time after the new workers were introduced, all of the newly intr...

    Text Solution

    |

  5. Mr. stenley employed a certain number of typist for his project. 8 day...

    Text Solution

    |

  6. Mr. stenley employed a certain number of typist for his project. 8 day...

    Text Solution

    |

  7. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  8. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  9. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  10. Five tailors A, B, C, D and E stich 1800 shirts in 90 days working alt...

    Text Solution

    |

  11. A man working 8 hours a day takes 5 days to complete a project. How ma...

    Text Solution

    |

  12. A person invests money in two different schemes for 5 years and 8 year...

    Text Solution

    |

  13. Eklavya can do the 6 times the actual work in 36 days while Faizal can...

    Text Solution

    |

  14. Progressive Company Pvt. Ltd. hired some employees in a fix pattern. O...

    Text Solution

    |

  15. Two persons having different productivity of labour, working together ...

    Text Solution

    |

  16. The total number of men, women and children working in a factory is 18...

    Text Solution

    |

  17. A group of workers was put on a job. From the second day onwards, one ...

    Text Solution

    |

  18. Two workers undertake to do a job. The second-worker started working 2...

    Text Solution

    |

  19. A group of men deaded to do a job in 4 days. But since 20 men dropped ...

    Text Solution

    |

  20. Brahma, Vishnu and Mahesh are three friends with different productivit...

    Text Solution

    |