A contract on construction job specifies...

A contract on construction job specifies a penalty for delay of completion beyond a certain days as follows: Rs. 180 for the first day, Rs. 200 for the second day, etc., the penalty for each succeeding day being Rs. 20 more than the preceding day. (i) How much money the contractor has to pay as penalty, if he has delayed the work by 15 days? (ii) For how many days has the contractor delayed the work if he paid Rs. 7400 as penalty?

Text Solution

Verified by Experts

The correct Answer is:
(i) Rs 4800 (ii) 20 days
Promotional Banner

Topper's Solved these Questions

  • ARITHMETIC PROGRESSIONS

    VK GLOBAL PUBLICATION|Exercise SELF ASSESSMENT TEST|10 Videos
  • ARITHMETIC PROGRESSIONS

    VK GLOBAL PUBLICATION|Exercise PROFICIENCY EXERCISE ( SHORT ANSWER QUESTION II)|39 Videos
  • AREAS RELATED TO CIRCLES

    VK GLOBAL PUBLICATION|Exercise Self -Assessment Test|11 Videos
  • CIRCLES

    VK GLOBAL PUBLICATION|Exercise SELF - ASSESSMENT TEST|11 Videos

Similar Questions

Explore conceptually related problems

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follow : Rs 500 for the first day , Rs 550 for the second day , Rs 600 for the third day , etc the penalty for each suceeding day being Rs 50 more than for the preceding day . How much money the contractor has to pay as penalty , if he has delayed the work by 50 days ?

A contract on construction job specifies a penalty for delay of completion beyond acertain date as follows: Rs 200 for Ist day,Rs.250 for second day,Rs.300 for thirdday and so on.If the contractor pays Rs 27750 as penalty, find the number of days forwhich the construction work is delayed.

If man A complete a work in 10 days & man B complete the same work in 15 days , in how many days the work is completed if they work together ?

Certain sum is sufficient to pay wage to A for 15 days or to B for 30 days. For how many days is the sum sufficient to pay both A and B?

18 men can earn Rs. 360 in 5 days . How much money will 15 men earn in 9 days ?

If you save Rs. 1 today, Rs. 2 the next day, Rs. 3 the succeeding day and so on, what will be your total savings in 365 days?

A can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?

Lalit earns Rs. x per day and spends Rs. y per day. How much does he save in 30 days?

Smith asked daddy to give Rs100 on first day and go on decreasing by Rs10 daily. How much money has he collected in 10 days?

VK GLOBAL PUBLICATION-ARITHMETIC PROGRESSIONS -PROFICIENCY EXERCISE ( LONG ANSWER QUESTIONS )
  1. Find the sum of the integers between 100 and 200 that are divisible by...

    Text Solution

    |

  2. Show that the sum of an AP whose first term is a, the second term b an...

    Text Solution

    |

  3. Sum of the first p, q and r terms of an A.P are a, b and c, respectiv...

    Text Solution

    |

  4. If the pth term of AP is 1/q and its q th term is 1/p show that sum of...

    Text Solution

    |

  5. The sum of the first five terms of an AP is 55 and sum of the first te...

    Text Solution

    |

  6. The ratio of the 11th term to the 18th term of an AP is 2:3. Find the ...

    Text Solution

    |

  7. A sum of Rs 2700 is to be used to give eight cash prizes to students o...

    Text Solution

    |

  8. Three hundred sixty bricks are stacked in the following manner: 30 bri...

    Text Solution

    |

  9. Reshma repays her total loan of Rs 1,75,000 by paying every month sta...

    Text Solution

    |

  10. The students of a shool decided to beautifly the school on the annual ...

    Text Solution

    |

  11. A man saved Rs 200 during the first month, Rs 225 in the second month ...

    Text Solution

    |

  12. A contract on construction job specifies a penalty for delay of comple...

    Text Solution

    |

  13. A manufacturer of wire produced 1400 m wire in the 5 th year and 1600 ...

    Text Solution

    |

  14. Find the middle term of the sequence formed by all three-digit numbers...

    Text Solution

    |

  15. Find the sum of all the two digit numbers which are either multiples o...

    Text Solution

    |

  16. Ramkali required Rs 2500 after 12 weeks to send her daughter to school...

    Text Solution

    |

  17. An arithmetic progression 5, 12, 19,..., has 50 terms. Find its last t...

    Text Solution

    |

  18. Find the middle term of the sequence formed by all numbers between 9 a...

    Text Solution

    |

  19. The sums of n terms of three arithmetical progressions are S1, S2a n d...

    Text Solution

    |

  20. If pth,qth and rth terms of an A.P. are a, b, c respectively, then sho...

    Text Solution

    |