If 12 men and 16 boys can do a piece of work in 5 days and, 13 men and 24 boys can do it in 4 days, how long will 7 men and 10 boys take to do it ?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first establish the relationships between men and boys in terms of work done, and then we will calculate how long it will take for 7 men and 10 boys to complete the same work. ### Step 1: Establish the equations based on the given information. 1. **Equation from the first scenario**: - 12 men and 16 boys can complete the work in 5 days. - Work done = (Number of workers) × (Time) - Work done = (12M + 16B) × 5 2. **Equation from the second scenario**: - 13 men and 24 boys can complete the work in 4 days. - Work done = (13M + 24B) × 4 Since both scenarios complete the same work, we can set the two equations equal to each other: \[ (12M + 16B) \times 5 = (13M + 24B) \times 4 \] ### Step 2: Expand and simplify the equations. 1. Expanding both sides: - Left side: \(60M + 80B\) - Right side: \(52M + 96B\) So, we have: \[ 60M + 80B = 52M + 96B \] ### Step 3: Rearranging the equation. 1. Move all terms involving M to one side and B to the other: \[ 60M - 52M = 96B - 80B \] \[ 8M = 16B \] ### Step 4: Find the relationship between M and B. 1. Dividing both sides by 8: \[ M = 2B \] ### Step 5: Substitute M in terms of B into the first equation. 1. Substitute \(M = 2B\) into the first work equation: \[ 12(2B) + 16B = 24B + 16B = 40B \] 2. So, the first equation becomes: \[ 40B \times 5 = 200B \] ### Step 6: Calculate the total work done. 1. The total work done by 12 men and 16 boys in 5 days is: \[ 200B \] ### Step 7: Calculate the work done by 7 men and 10 boys. 1. First, express 7 men and 10 boys in terms of boys: - 7 men = \(7 \times 2B = 14B\) - 10 boys = \(10B\) - Total = \(14B + 10B = 24B\) ### Step 8: Set up the equation for time taken by 7 men and 10 boys. 1. Let \(X\) be the number of days it takes for 7 men and 10 boys to complete the work: \[ 24B \times X = 200B \] ### Step 9: Solve for X. 1. Dividing both sides by \(24B\): \[ X = \frac{200B}{24B} = \frac{200}{24} = \frac{25}{3} \approx 8.33 \text{ days} \] ### Final Answer: The time taken by 7 men and 10 boys to complete the work is approximately **8.33 days**.
Promotional Banner

Topper's Solved these Questions

  • DIRECT AND INVERSE VARIATIONS

    ICSE|Exercise EXERCISE 10 (D)|13 Videos
  • DIRECT AND INVERSE VARIATIONS

    ICSE|Exercise EXERCISE 10 (E)|19 Videos
  • DIRECT AND INVERSE VARIATIONS

    ICSE|Exercise EXERCISE 10 (B)|11 Videos
  • DATA HANDLING

    ICSE|Exercise EXERCISE 22 (B) |10 Videos
  • EXPONENTS (POWERS)

    ICSE|Exercise EXERCISE 2(B)|50 Videos

Similar Questions

Explore conceptually related problems

3 men and 4 boys can do a piece of work in 14 days, while 4 men and 6 boys can do it in 10 days. How long would it take 1 boy to finish the work?

10 boys can dig a pitch in 12 hours. How long will 8 boys take to do it?

6 men and 8 boys can do a piece of work in 7 days, while 8 men and 12 boys do the same work in 5 days. How long would it take one boy to finish the same work?

If 3 men or 6 boys can finish a work in 20 days, how long will 4 men and 12 boys take to finish the same work ?

If 56 men can do a piece of work in 42 days. How many men will do it in 14 days?

Amit can do a piece of work in 4 days and Sumit can do it in 6 days How long will they take, if both Amit and Sumit work together ?

If 12 women can do a piece of work in 9 days, in how many days can 18 women do it ?

36 men can do a piece of work in 7 days. How many men will do the same work in 42 days ?

If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?

If 52 men can do a piece of work in 35 days in how many days 28 men will do it ?

ICSE-DIRECT AND INVERSE VARIATIONS-EXERCISE 10 C
  1. Cost of 24 identical articals Rs. 108. Find the cost of 40 similar art...

    Text Solution

    |

  2. If 15 men can complete a piece of work in 30 days, in how many days wi...

    Text Solution

    |

  3. In order to complete a work in 28 days, 60 men are required. How Mny m...

    Text Solution

    |

  4. A fort had provisions for 450 soldiers for 40 days. After 10 days, 90 ...

    Text Solution

    |

  5. A garrison has sufficient provisions for 480 men for 12 days. If the n...

    Text Solution

    |

  6. (3)/(5) quital of wheat cost Rs. 210. find the cost of : 1 quintal o...

    Text Solution

    |

  7. (3)/(5) quital of wheat cost Rs. 210. find the cost of : 0.4 quintal...

    Text Solution

    |

  8. If (2)/(9) of a property costs Rs. 2,52,00, find the cost of (4)/(7) o...

    Text Solution

    |

  9. 4 men or 6 women earn Rs. 360 in one days. Find, how much will : A m...

    Text Solution

    |

  10. 4 men or 6 women earn Rs. 360 in one days. Find, how much will : A w...

    Text Solution

    |

  11. 4 men or 6 women earn Rs. 360 in one days. Find, how much will : A m...

    Text Solution

    |

  12. 16 boys went to a canteen to have tea and snacks together. The bill am...

    Text Solution

    |

  13. 50 labourers can dig a point in 16 days. How many labourers will be re...

    Text Solution

    |

  14. If 12 men or 18 women can complete a piece of work in 7 days, in how m...

    Text Solution

    |

  15. If 3 men or 6 boys can finish a work in 20 days, how long will 4 men a...

    Text Solution

    |

  16. A particular work can be completed by 6 men and 6 women in 24 days, wh...

    Text Solution

    |

  17. A particular work can be completed by 6 men and 6 women in 24 days, wh...

    Text Solution

    |

  18. If 12 men and 16 boys can do a piece of work in 5 days and, 13 men and...

    Text Solution

    |