A and B can do a piece of work in 45 ...

A and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some das and B finished the remaining work in 23 days. After how many days did A leave?

Text Solution

Verified by Experts

The correct Answer is:
9 days
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Question Bank - 13(a)|30 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Question Bank - 13(b)|15 Videos
  • SIMPLE INTEREST

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet |10 Videos
  • TRIANGLES

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 18|10 Videos

Similar Questions

Explore conceptually related problems

A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave

A and B can do a piece of work in 45 and 40 days respectively.They began the work together but A leaves after some days and B finished the remaining work in 23 days.After how many days did A leave?

A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?

A and B can do a piece of work in 28 and 35 days respectively.They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave? 7(5)/(9) days b. 8) days c.9backslash days d.14(2)/(5) days

A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?

S CHAND IIT JEE FOUNDATION-TIME AND WORK -Self Assessment Sheet - 13
  1. A and B can do a piece of work in 45 and 40 days respectively. They...

    Text Solution

    |

  2. A alone can complete a piece of work in 6 days and B alone can complet...

    Text Solution

    |

  3. Kamal can do a work n 15 days. Bimal is 50% more efficient than Kam...

    Text Solution

    |

  4. A man and a boy can do a piece of work in 24 days. If the man works...

    Text Solution

    |

  5. A and B together can do a piece of work in 6 days. A alone can do it i...

    Text Solution

    |

  6. A' can do a piece of work in 4 days and B in 12 days. In how many days...

    Text Solution

    |

  7. Two men undertake to do a piece of work for Rs. 1400. The first man...

    Text Solution

    |

  8. A and B can do a piece of work in 8 days, B and C can do the same work...

    Text Solution

    |

  9. Two taps can fill a tub in 5 minutes and 7 minutes respectively. A pip...

    Text Solution

    |

  10. A man completes 4/9 of a job in 12 days. At this rate, how many more d...

    Text Solution

    |

  11. Three workers, working all days can do a work in 10 days, but one of t...

    Text Solution

    |

  12. A tap fills a tank in 12 hours and the other empties it in 24 hours. I...

    Text Solution

    |

  13. If 15 pumps of equal capacity can fill a tank in 7 days, then how many...

    Text Solution

    |

  14. A tap can fill a tank in 6 hours. After half the tank is filled, th...

    Text Solution

    |

  15. If three taps are opened together, a tank is filled in 12 hours. One o...

    Text Solution

    |

  16. A can do a work in 18 days, B in 9 days and C in 6 days. A and B start...

    Text Solution

    |