Home
Class 14
MATHS
A and B together can complete a work in ...

A and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work?

A

8 days

B

10 days

C

12 days

D

20 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work rates of A, B, and C based on the information provided. ### Step 1: Determine the work done by A and B together. A and B together can complete the work in 8 days. Therefore, the amount of work they can do in one day is: \[ \text{Work rate of A + B} = \frac{1}{8} \text{ (work per day)} \] If we consider the total work to be 24 units, then: \[ \text{Work done by A + B in 1 day} = \frac{24}{8} = 3 \text{ units} \] ### Step 2: Determine the work done by B and C together. B and C together can complete the work in 12 days. Therefore, their work rate is: \[ \text{Work rate of B + C} = \frac{1}{12} \text{ (work per day)} \] Thus, the work done by B and C in one day is: \[ \text{Work done by B + C in 1 day} = \frac{24}{12} = 2 \text{ units} \] ### Step 3: Determine the work done by A, B, and C together. A, B, and C together can complete the work in 6 days. Therefore, their work rate is: \[ \text{Work rate of A + B + C} = \frac{1}{6} \text{ (work per day)} \] Thus, the work done by A, B, and C in one day is: \[ \text{Work done by A + B + C in 1 day} = \frac{24}{6} = 4 \text{ units} \] ### Step 4: Set up equations for the work rates. From the above calculations, we have: - A + B = 3 units/day - B + C = 2 units/day - A + B + C = 4 units/day ### Step 5: Find the work done by A and C together. To find the work done by A and C together, we can use the following relationship: \[ \text{(A + C)} = \text{(A + B + C)} - \text{(B)} \] We can express B in terms of the other equations. From A + B + C = 4 units and B + C = 2 units, we can find B: \[ B = (A + B + C) - (A + C) = 4 - (A + C) \] Now, substituting the value of B from B + C: \[ B + C = 2 \implies (4 - (A + C)) + C = 2 \] This simplifies to: \[ 4 - A = 2 \implies A = 2 \text{ units} \] ### Step 6: Substitute to find C. Now substituting A back into A + B = 3: \[ 2 + B = 3 \implies B = 1 \text{ unit} \] Now substituting B into B + C = 2: \[ 1 + C = 2 \implies C = 1 \text{ unit} \] ### Step 7: Calculate A + C. Now we can find A + C: \[ A + C = 2 + 1 = 3 \text{ units/day} \] ### Step 8: Calculate the time taken by A and C to complete the work. To find the time taken by A and C together to complete the work: \[ \text{Time} = \frac{\text{Total Work}}{\text{Work Rate of A + C}} = \frac{24}{3} = 8 \text{ days} \] ### Final Answer: A and C together can complete the work in **8 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-II|45 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?

If A can complete work in 6 days, B can complete the work in 8 days and C can complete the same work in 12 days. In how much time A, B, and C can complete the work.

A and B together can complete a work in 12 days,B and C together can complete the same work in 8 days and A and C together can complete it in 16 days.In total,how many days do A,B and C together take to complete the same work? 3(5)/(12) b.3(9)/(13) c.7(5)/(12) d.7(5)/(13) e. none of these

A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

In how many days will B alone complete the work? I. A and B together can complete the work in 8 days. II. B and C together can complete the work in 10 days. III. A and C together can complete the work in 12 days

To complete a certain work, C working alone takes twice as long as A and B working together. A working alone takes 3 times as long as B and C working together. All the three together can complete the work in 5 days. How long would each take to complete th work individually?

KIRAN PUBLICATION-TIME AND WORK-TEST YOURSELF
  1. A and B together can complete a work in 8 days and B and C together in...

    Text Solution

    |

  2. A contract to be completed in 56 days and 104 men were set towork each...

    Text Solution

    |

  3. 12 men and 18 boys working 7(1)/(2) hours a day can do a work in 60 da...

    Text Solution

    |

  4. If A alone can do a work in 12 days and B alone can do it in 8 days, W...

    Text Solution

    |

  5. A and B can do a work in 8 days. B alone can do it in 24 days. In how ...

    Text Solution

    |

  6. A can do (1)/(2) of a work in 9 days while B can do (1)/(3) of the sam...

    Text Solution

    |

  7. A can do a work in 12 days and B can do it in 16 days. A and B started...

    Text Solution

    |

  8. Ram can do a piece of work in 20 days and Shyam in 30 days. They work ...

    Text Solution

    |

  9. A and B can complete a piece of work in 45 and 40 days respectively. B...

    Text Solution

    |

  10. A can do a piece of work in 40 days. He works on it for 5 days and the...

    Text Solution

    |

  11. Rita, Sita and Meeta are employed to do a piece of work for Rs 625. Ri...

    Text Solution

    |

  12. A and B can do a piece of work in 10 days, B and C in 15 days and C an...

    Text Solution

    |

  13. A, B and C can complete a work In 8 days. B alone can do it in 18 days...

    Text Solution

    |

  14. A alone takes as much time as B and C together take to complete a piec...

    Text Solution

    |

  15. A and B together can finish a work in 15 days. A and C take 2 days mor...

    Text Solution

    |

  16. A and B together can do a piece of work in 30 days, B and C together c...

    Text Solution

    |

  17. A and B can do a piece of work in 12 days, B and C in 15 days, C and A...

    Text Solution

    |

  18. A can complete a work in 24 days, B in 32 days and C in 64 days. They ...

    Text Solution

    |

  19. A, B and C can complete a work separately in 24, 36 and 48 days respec...

    Text Solution

    |

  20. A can complete a work in 10 days, B can complete the same work in 20 d...

    Text Solution

    |

  21. A can do a piece of work in 120 days and B can do it in 150 days. They...

    Text Solution

    |