A can do a piece of work in 25 days and B can do the same work in 30 days. They work together for 5 days, how much of work is left?

A

`(11)/(30)`

B

`(15)/(30)`

C

`(19)/(30)`

D

`(12)/(30)`

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-II|45 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

Deepak can do a piece of work in 25 days and Ashok can do the same work in 40 days.They work together for 5days and then Deepak goes away.In how many days will Ashok finish the remaining work?

A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?

A can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?

A can do a piece of work in 9 days and B can do the same work in 15 days. If they work together, in what ratio A and B will receive their wages?

P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?

A can do a piece of work in 25 days and B can finish it in 20 days.They work together for 5 days and then A goes away.In how many days will B finish the remaining work?

A can do a work in 20 days and B can do it in 14 days. If they work together for 7 days, then the fraction of the work left is:

A can do a piece of work in 16 days and B can do the same work in 20 days.In how many days can they do the same work,working together?

KIRAN PUBLICATION-TIME AND WORK-TEST YOURSELF
  1. A can do a piece of work in 25 days and B can do the same work in 30 d...

    Text Solution

    |

  2. A contract to be completed in 56 days and 104 men were set towork each...

    Text Solution

    |

  3. 12 men and 18 boys working 7(1)/(2) hours a day can do a work in 60 da...

    Text Solution

    |

  4. If A alone can do a work in 12 days and B alone can do it in 8 days, W...

    Text Solution

    |

  5. A and B can do a work in 8 days. B alone can do it in 24 days. In how ...

    Text Solution

    |

  6. A can do (1)/(2) of a work in 9 days while B can do (1)/(3) of the sam...

    Text Solution

    |

  7. A can do a work in 12 days and B can do it in 16 days. A and B started...

    Text Solution

    |

  8. Ram can do a piece of work in 20 days and Shyam in 30 days. They work ...

    Text Solution

    |

  9. A and B can complete a piece of work in 45 and 40 days respectively. B...

    Text Solution

    |

  10. A can do a piece of work in 40 days. He works on it for 5 days and the...

    Text Solution

    |

  11. Rita, Sita and Meeta are employed to do a piece of work for Rs 625. Ri...

    Text Solution

    |

  12. A and B can do a piece of work in 10 days, B and C in 15 days and C an...

    Text Solution

    |

  13. A, B and C can complete a work In 8 days. B alone can do it in 18 days...

    Text Solution

    |

  14. A alone takes as much time as B and C together take to complete a piec...

    Text Solution

    |

  15. A and B together can finish a work in 15 days. A and C take 2 days mor...

    Text Solution

    |

  16. A and B together can do a piece of work in 30 days, B and C together c...

    Text Solution

    |

  17. A and B can do a piece of work in 12 days, B and C in 15 days, C and A...

    Text Solution

    |

  18. A can complete a work in 24 days, B in 32 days and C in 64 days. They ...

    Text Solution

    |

  19. A, B and C can complete a work separately in 24, 36 and 48 days respec...

    Text Solution

    |

  20. A can complete a work in 10 days, B can complete the same work in 20 d...

    Text Solution

    |

  21. A can do a piece of work in 120 days and B can do it in 150 days. They...

    Text Solution

    |