Home
Class 14
MATHS
A can do a piece of work in 18 days. He ...

A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in

A

16 days

B

24 days

C

28 days

D

29 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine A's Efficiency A can complete the work in 18 days. We can assume that the total work is 1800 units (for easier calculations). Thus, A's efficiency can be calculated as: \[ \text{Efficiency of A} = \frac{\text{Total Work}}{\text{Time taken by A}} = \frac{1800 \text{ units}}{18 \text{ days}} = 100 \text{ units/day} \] **Hint:** To find efficiency, divide the total work by the time taken to complete that work. ### Step 2: Calculate Work Done by A in 12 Days A worked for 12 days. The amount of work done by A in these 12 days is: \[ \text{Work done by A} = \text{Efficiency of A} \times \text{Days worked} = 100 \text{ units/day} \times 12 \text{ days} = 1200 \text{ units} \] **Hint:** Multiply the efficiency by the number of days worked to find the total work done. ### Step 3: Calculate Remaining Work The total work is 1800 units, and A has completed 1200 units. Therefore, the remaining work is: \[ \text{Remaining Work} = \text{Total Work} - \text{Work done by A} = 1800 \text{ units} - 1200 \text{ units} = 600 \text{ units} \] **Hint:** Subtract the work done from the total work to find out how much is left. ### Step 4: Determine B's Efficiency B finished the remaining 600 units of work in 8 days. Therefore, B's efficiency can be calculated as: \[ \text{Efficiency of B} = \frac{\text{Remaining Work}}{\text{Time taken by B}} = \frac{600 \text{ units}}{8 \text{ days}} = 75 \text{ units/day} \] **Hint:** To find efficiency, divide the amount of work completed by the time taken to complete that work. ### Step 5: Calculate Time for B to Complete the Whole Work Alone Now, we need to find out how long it would take B to complete the entire 1800 units of work alone. We can use the efficiency of B: \[ \text{Time taken by B to complete the whole work} = \frac{\text{Total Work}}{\text{Efficiency of B}} = \frac{1800 \text{ units}}{75 \text{ units/day}} = 24 \text{ days} \] **Hint:** To find the time taken to complete the whole work, divide the total work by the efficiency. ### Conclusion B alone can complete the whole work in **24 days**. ### Final Answer B alone can do the whole work in **24 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-II|45 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 80 days.He works at it for 10 days and then B alore finishes the remaining work in 42 days.How long will B take to do the entire work alone?

Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?

A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

Abhishek can do a piece of work in 40 days. He alone worked at it for 8 days and then Bacchhan completed alone the rest work in 24 days. In how many days they will complete the whole work, working together ?

Abhishek can do a piece of work in 40 days. He alone worked at it for 8 days and then Bacchhan completed alone the rest work in 24 days. In how many days they will complete the whole work, working together?

KIRAN PUBLICATION-TIME AND WORK-TEST YOURSELF
  1. A can do a piece of work in 18 days. He worked at it for 12 days and B...

    Text Solution

    |

  2. A contract to be completed in 56 days and 104 men were set towork each...

    Text Solution

    |

  3. 12 men and 18 boys working 7(1)/(2) hours a day can do a work in 60 da...

    Text Solution

    |

  4. If A alone can do a work in 12 days and B alone can do it in 8 days, W...

    Text Solution

    |

  5. A and B can do a work in 8 days. B alone can do it in 24 days. In how ...

    Text Solution

    |

  6. A can do (1)/(2) of a work in 9 days while B can do (1)/(3) of the sam...

    Text Solution

    |

  7. A can do a work in 12 days and B can do it in 16 days. A and B started...

    Text Solution

    |

  8. Ram can do a piece of work in 20 days and Shyam in 30 days. They work ...

    Text Solution

    |

  9. A and B can complete a piece of work in 45 and 40 days respectively. B...

    Text Solution

    |

  10. A can do a piece of work in 40 days. He works on it for 5 days and the...

    Text Solution

    |

  11. Rita, Sita and Meeta are employed to do a piece of work for Rs 625. Ri...

    Text Solution

    |

  12. A and B can do a piece of work in 10 days, B and C in 15 days and C an...

    Text Solution

    |

  13. A, B and C can complete a work In 8 days. B alone can do it in 18 days...

    Text Solution

    |

  14. A alone takes as much time as B and C together take to complete a piec...

    Text Solution

    |

  15. A and B together can finish a work in 15 days. A and C take 2 days mor...

    Text Solution

    |

  16. A and B together can do a piece of work in 30 days, B and C together c...

    Text Solution

    |

  17. A and B can do a piece of work in 12 days, B and C in 15 days, C and A...

    Text Solution

    |

  18. A can complete a work in 24 days, B in 32 days and C in 64 days. They ...

    Text Solution

    |

  19. A, B and C can complete a work separately in 24, 36 and 48 days respec...

    Text Solution

    |

  20. A can complete a work in 10 days, B can complete the same work in 20 d...

    Text Solution

    |

  21. A can do a piece of work in 120 days and B can do it in 150 days. They...

    Text Solution

    |