A canal of a village can be cleaned by 2...

A canal of a village can be cleaned by 24 villagers in 12 days. The number of days in which 36 villagers can clean the canal is?

A

18

B

8

C

72

D

16

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-II|45 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

There are 5 roads leading to a town from a village.The number of different ways in which a villager can go to the town and return back, is

If 20 persons can clean 20 floors in 20 days, then in how many days can 16 persons clean 16 floors?

Find the number of ways in which 16 constables can be assigned to patrol villages,2 for each.

In a village A, Number of male is twice number of female. Ratio of the male in village A & village B is 1:3. If the number of female in village B is 78, and total population in both villages is 978. What is the number of female in village A?

Study the following information carefully and answer the given questions: In the diagram, Population Density (in population per square kilometer) and Land Area (in square kilometer) of 4 villages A, B, C and D for the year 2001 is given. Population Density of a village = Total population of the village / Area (in square km) of the land of the village Gender Ratio of a village = (Total number of males in a village/Total number of females in a village) xx 100 Gender ratio of village C is 125 less than that of A . If female population of villages A and C are equal, then find the male population in village A

The population of a village was 9800. In a year, with the increase in population of males by 8% and that of females by 5%, the population of the village became 10458. What was the number of males in the village before increase?

KIRAN PUBLICATION-TIME AND WORK-TEST YOURSELF
  1. A canal of a village can be cleaned by 24 villagers in 12 days. The nu...

    Text Solution

    |

  2. A contract to be completed in 56 days and 104 men were set towork each...

    Text Solution

    |

  3. 12 men and 18 boys working 7(1)/(2) hours a day can do a work in 60 da...

    Text Solution

    |

  4. If A alone can do a work in 12 days and B alone can do it in 8 days, W...

    Text Solution

    |

  5. A and B can do a work in 8 days. B alone can do it in 24 days. In how ...

    Text Solution

    |

  6. A can do (1)/(2) of a work in 9 days while B can do (1)/(3) of the sam...

    Text Solution

    |

  7. A can do a work in 12 days and B can do it in 16 days. A and B started...

    Text Solution

    |

  8. Ram can do a piece of work in 20 days and Shyam in 30 days. They work ...

    Text Solution

    |

  9. A and B can complete a piece of work in 45 and 40 days respectively. B...

    Text Solution

    |

  10. A can do a piece of work in 40 days. He works on it for 5 days and the...

    Text Solution

    |

  11. Rita, Sita and Meeta are employed to do a piece of work for Rs 625. Ri...

    Text Solution

    |

  12. A and B can do a piece of work in 10 days, B and C in 15 days and C an...

    Text Solution

    |

  13. A, B and C can complete a work In 8 days. B alone can do it in 18 days...

    Text Solution

    |

  14. A alone takes as much time as B and C together take to complete a piec...

    Text Solution

    |

  15. A and B together can finish a work in 15 days. A and C take 2 days mor...

    Text Solution

    |

  16. A and B together can do a piece of work in 30 days, B and C together c...

    Text Solution

    |

  17. A and B can do a piece of work in 12 days, B and C in 15 days, C and A...

    Text Solution

    |

  18. A can complete a work in 24 days, B in 32 days and C in 64 days. They ...

    Text Solution

    |

  19. A, B and C can complete a work separately in 24, 36 and 48 days respec...

    Text Solution

    |

  20. A can complete a work in 10 days, B can complete the same work in 20 d...

    Text Solution

    |

  21. A can do a piece of work in 120 days and B can do it in 150 days. They...

    Text Solution

    |