If 7 men or 10 women can make a 100 mete...

If 7 men or 10 women can make a 100 meters wall in 10 days, in how many days 14 men and 20 women can make a 600 m wall?

A

15

B

20

C

25

D

30

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-II|45 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

6 men or 8 women can do a job in 10 days In how many days can 5 men and 9 women do the same job?

Five men or ten women can complete a job in 20 days. In how many days can 3 men and 4 women complete it ?

If 12 men or 18 women can do a work in 14 days,then in how many days will 8 men and 16 women do the same work?

If 3 men and 4 women can build a wall in 43 days , in how many days can 7 men and 5 women build this wall ?

If 4 men or 7 women can do a work in 60 days, then in how many days will 8 men and 7 women finish the same work?

3 men or 4 women can do a piece of work in 43 days. In how many days 7 men & 5 women can do the same work ?

If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?

KIRAN PUBLICATION-TIME AND WORK-TEST YOURSELF
  1. If 7 men or 10 women can make a 100 meters wall in 10 days, in how man...

    Text Solution

    |

  2. A contract to be completed in 56 days and 104 men were set towork each...

    Text Solution

    |

  3. 12 men and 18 boys working 7(1)/(2) hours a day can do a work in 60 da...

    Text Solution

    |

  4. If A alone can do a work in 12 days and B alone can do it in 8 days, W...

    Text Solution

    |

  5. A and B can do a work in 8 days. B alone can do it in 24 days. In how ...

    Text Solution

    |

  6. A can do (1)/(2) of a work in 9 days while B can do (1)/(3) of the sam...

    Text Solution

    |

  7. A can do a work in 12 days and B can do it in 16 days. A and B started...

    Text Solution

    |

  8. Ram can do a piece of work in 20 days and Shyam in 30 days. They work ...

    Text Solution

    |

  9. A and B can complete a piece of work in 45 and 40 days respectively. B...

    Text Solution

    |

  10. A can do a piece of work in 40 days. He works on it for 5 days and the...

    Text Solution

    |

  11. Rita, Sita and Meeta are employed to do a piece of work for Rs 625. Ri...

    Text Solution

    |

  12. A and B can do a piece of work in 10 days, B and C in 15 days and C an...

    Text Solution

    |

  13. A, B and C can complete a work In 8 days. B alone can do it in 18 days...

    Text Solution

    |

  14. A alone takes as much time as B and C together take to complete a piec...

    Text Solution

    |

  15. A and B together can finish a work in 15 days. A and C take 2 days mor...

    Text Solution

    |

  16. A and B together can do a piece of work in 30 days, B and C together c...

    Text Solution

    |

  17. A and B can do a piece of work in 12 days, B and C in 15 days, C and A...

    Text Solution

    |

  18. A can complete a work in 24 days, B in 32 days and C in 64 days. They ...

    Text Solution

    |

  19. A, B and C can complete a work separately in 24, 36 and 48 days respec...

    Text Solution

    |

  20. A can complete a work in 10 days, B can complete the same work in 20 d...

    Text Solution

    |

  21. A can do a piece of work in 120 days and B can do it in 150 days. They...

    Text Solution

    |