Home
Class 14
MATHS
Some carpenters promised to do a job in ...

Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was

A

24

B

20

C

16

D

18

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow this approach: ### Step 1: Define the Variables Let the original number of carpenters be \( x \). ### Step 2: Calculate Total Work The carpenters promised to complete the job in 9 days. Therefore, the total work can be expressed as: \[ \text{Total Work} = \text{Number of Carpenters} \times \text{Days} = x \times 9 = 9x \] ### Step 3: Calculate Work Done by Remaining Carpenters Since 5 carpenters were absent, the number of carpenters who actually worked is: \[ x - 5 \] They completed the job in 12 days, so the total work done can also be expressed as: \[ \text{Total Work} = \text{Number of Remaining Carpenters} \times \text{Days} = (x - 5) \times 12 \] ### Step 4: Set Up the Equation Since both expressions represent the total work, we can set them equal to each other: \[ 9x = 12(x - 5) \] ### Step 5: Expand and Simplify the Equation Expanding the right side: \[ 9x = 12x - 60 \] Now, rearranging the equation to isolate \( x \): \[ 9x - 12x = -60 \] \[ -3x = -60 \] ### Step 6: Solve for \( x \) Dividing both sides by -3: \[ x = 20 \] ### Conclusion The original number of carpenters was \( 20 \). ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-II|45 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :

A group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?

6 men or 8 women can do a job in 10 days In how many days can 5 men and 9 women do the same job?

24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

If 30 men can do a job in 30 days, find what part of the job can be completed by 1 man in 1 day.

If 12 men can do a job in 7 days, what fraction of the job can be done by one man in one day?

KIRAN PUBLICATION-TIME AND WORK-TEST YOURSELF
  1. Some carpenters promised to do a job in 9 days but 5 of them were abse...

    Text Solution

    |

  2. A contract to be completed in 56 days and 104 men were set towork each...

    Text Solution

    |

  3. 12 men and 18 boys working 7(1)/(2) hours a day can do a work in 60 da...

    Text Solution

    |

  4. If A alone can do a work in 12 days and B alone can do it in 8 days, W...

    Text Solution

    |

  5. A and B can do a work in 8 days. B alone can do it in 24 days. In how ...

    Text Solution

    |

  6. A can do (1)/(2) of a work in 9 days while B can do (1)/(3) of the sam...

    Text Solution

    |

  7. A can do a work in 12 days and B can do it in 16 days. A and B started...

    Text Solution

    |

  8. Ram can do a piece of work in 20 days and Shyam in 30 days. They work ...

    Text Solution

    |

  9. A and B can complete a piece of work in 45 and 40 days respectively. B...

    Text Solution

    |

  10. A can do a piece of work in 40 days. He works on it for 5 days and the...

    Text Solution

    |

  11. Rita, Sita and Meeta are employed to do a piece of work for Rs 625. Ri...

    Text Solution

    |

  12. A and B can do a piece of work in 10 days, B and C in 15 days and C an...

    Text Solution

    |

  13. A, B and C can complete a work In 8 days. B alone can do it in 18 days...

    Text Solution

    |

  14. A alone takes as much time as B and C together take to complete a piec...

    Text Solution

    |

  15. A and B together can finish a work in 15 days. A and C take 2 days mor...

    Text Solution

    |

  16. A and B together can do a piece of work in 30 days, B and C together c...

    Text Solution

    |

  17. A and B can do a piece of work in 12 days, B and C in 15 days, C and A...

    Text Solution

    |

  18. A can complete a work in 24 days, B in 32 days and C in 64 days. They ...

    Text Solution

    |

  19. A, B and C can complete a work separately in 24, 36 and 48 days respec...

    Text Solution

    |

  20. A can complete a work in 10 days, B can complete the same work in 20 d...

    Text Solution

    |

  21. A can do a piece of work in 120 days and B can do it in 150 days. They...

    Text Solution

    |