Home
Class 14
MATHS
A contractor undertook to finish a certa...

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done `(2)/(3)` of the work. How many men can be discharge now so that the work may finish in time?

A

48

B

56

C

40

D

50

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the reasoning laid out in the video transcript. ### Step 1: Understand the total work and the initial setup The contractor has a total of 124 days to complete the work with 120 men. ### Step 2: Calculate the work done in the first 64 days In the first 64 days, the contractor completed \( \frac{2}{3} \) of the work. ### Step 3: Determine the remaining work The remaining work after 64 days is: \[ \text{Remaining work} = 1 - \frac{2}{3} = \frac{1}{3} \] ### Step 4: Calculate the remaining days The total time is 124 days, and 64 days have already been used. Therefore, the remaining days are: \[ \text{Remaining days} = 124 - 64 = 60 \text{ days} \] ### Step 5: Set up the equation for the remaining work Let \( x \) be the number of men to be discharged. The number of men remaining after discharging \( x \) men will be: \[ 120 - x \] The work done by \( 120 - x \) men in the remaining 60 days must equal the remaining \( \frac{1}{3} \) of the work. ### Step 6: Calculate the work done by the original setup The work done by 120 men in 64 days can be expressed as: \[ \text{Work done} = 120 \text{ men} \times 64 \text{ days} \] ### Step 7: Set up the equation for the remaining work The work done by \( 120 - x \) men in 60 days is: \[ \text{Work done} = (120 - x) \text{ men} \times 60 \text{ days} \] Setting the work done equal to the remaining work: \[ (120 - x) \times 60 = \frac{1}{3} \times (120 \times 124) \] ### Step 8: Calculate the total work The total work can be calculated as: \[ \text{Total work} = 120 \text{ men} \times 124 \text{ days} = 14880 \text{ man-days} \] Thus, the remaining work is: \[ \frac{1}{3} \times 14880 = 4960 \text{ man-days} \] ### Step 9: Set up the final equation Now we can equate: \[ (120 - x) \times 60 = 4960 \] ### Step 10: Solve for \( x \) Expanding the equation gives: \[ 7200 - 60x = 4960 \] Rearranging gives: \[ 60x = 7200 - 4960 \] \[ 60x = 2240 \] \[ x = \frac{2240}{60} = 37.33 \] Since \( x \) must be a whole number, we round it to \( 37 \). ### Conclusion The contractor can discharge **37 men** to finish the work on time.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-II|45 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 2/3 of the work. How many men can be discharged now so that the work inay finish in time?

A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extre men should he employ so that the work is completed on time?

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?

A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that (1)/(3)rd of the work was still to be done. How many more men were required to complete the work in stipulated time?

90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is: (A) 50 (B) 75 (C) 100 (D) 150

36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in time?

KIRAN PUBLICATION-TIME AND WORK-TEST YOURSELF
  1. A contractor undertook to finish a certain work in 124 days and employ...

    Text Solution

    |

  2. A contract to be completed in 56 days and 104 men were set towork each...

    Text Solution

    |

  3. 12 men and 18 boys working 7(1)/(2) hours a day can do a work in 60 da...

    Text Solution

    |

  4. If A alone can do a work in 12 days and B alone can do it in 8 days, W...

    Text Solution

    |

  5. A and B can do a work in 8 days. B alone can do it in 24 days. In how ...

    Text Solution

    |

  6. A can do (1)/(2) of a work in 9 days while B can do (1)/(3) of the sam...

    Text Solution

    |

  7. A can do a work in 12 days and B can do it in 16 days. A and B started...

    Text Solution

    |

  8. Ram can do a piece of work in 20 days and Shyam in 30 days. They work ...

    Text Solution

    |

  9. A and B can complete a piece of work in 45 and 40 days respectively. B...

    Text Solution

    |

  10. A can do a piece of work in 40 days. He works on it for 5 days and the...

    Text Solution

    |

  11. Rita, Sita and Meeta are employed to do a piece of work for Rs 625. Ri...

    Text Solution

    |

  12. A and B can do a piece of work in 10 days, B and C in 15 days and C an...

    Text Solution

    |

  13. A, B and C can complete a work In 8 days. B alone can do it in 18 days...

    Text Solution

    |

  14. A alone takes as much time as B and C together take to complete a piec...

    Text Solution

    |

  15. A and B together can finish a work in 15 days. A and C take 2 days mor...

    Text Solution

    |

  16. A and B together can do a piece of work in 30 days, B and C together c...

    Text Solution

    |

  17. A and B can do a piece of work in 12 days, B and C in 15 days, C and A...

    Text Solution

    |

  18. A can complete a work in 24 days, B in 32 days and C in 64 days. They ...

    Text Solution

    |

  19. A, B and C can complete a work separately in 24, 36 and 48 days respec...

    Text Solution

    |

  20. A can complete a work in 10 days, B can complete the same work in 20 d...

    Text Solution

    |

  21. A can do a piece of work in 120 days and B can do it in 150 days. They...

    Text Solution

    |