Home
Class 14
MATHS
A can do a piece of work in 6 days worki...

A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?

A

4

B

`5(4)/(11)`

C

`6(4)/(11)`

D

`4(4)/(11)`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we need to determine how many hours A and B need to work together each day to complete the work in 5 days. ### Step 1: Calculate the total work done by A and B. - **A's Work Calculation:** A can complete the work in 6 days, working 8 hours a day. \[ \text{Total work by A} = 6 \text{ days} \times 8 \text{ hours/day} = 48 \text{ hours} \] - **B's Work Calculation:** B can complete the work in 4 days, working 10 hours a day. \[ \text{Total work by B} = 4 \text{ days} \times 10 \text{ hours/day} = 40 \text{ hours} \] ### Step 2: Determine the total amount of work required. The total work required to complete the task is the same as the work done by A or B, which is the maximum of the two: \[ \text{Total Work} = 48 \text{ hours} \text{ (A's work)} \] ### Step 3: Calculate the work done per hour by A and B. - **A's Work Rate:** \[ \text{Work rate of A} = \frac{1 \text{ work}}{48 \text{ hours}} = \frac{1}{48} \text{ work/hour} \] - **B's Work Rate:** \[ \text{Work rate of B} = \frac{1 \text{ work}}{40 \text{ hours}} = \frac{1}{40} \text{ work/hour} \] ### Step 4: Combine their work rates. To find the combined work rate of A and B: \[ \text{Combined work rate} = \frac{1}{48} + \frac{1}{40} \] To add these fractions, we need a common denominator. The least common multiple of 48 and 40 is 240. Converting the fractions: \[ \frac{1}{48} = \frac{5}{240}, \quad \frac{1}{40} = \frac{6}{240} \] So, \[ \text{Combined work rate} = \frac{5}{240} + \frac{6}{240} = \frac{11}{240} \text{ work/hour} \] ### Step 5: Calculate the total work needed in 5 days. If they need to complete the work in 5 days, the total work done in 5 days at their combined work rate is: \[ \text{Total work in 5 days} = 5 \text{ days} \times H \text{ hours/day} \times \frac{11}{240} \text{ work/hour} \] Setting this equal to 1 (the total work): \[ 5H \cdot \frac{11}{240} = 1 \] ### Step 6: Solve for H. Rearranging the equation: \[ H = \frac{240}{5 \times 11} = \frac{240}{55} = \frac{48}{11} \] ### Step 7: Convert hours into a mixed number. \[ H = 4 \frac{4}{11} \text{ hours} \] ### Final Answer: A and B need to work together for approximately \(4 \frac{4}{11}\) hours each day to complete the work in 5 days. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-II|45 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?

A can do a piece of work in 16 days and B can do the same work in 20 days.In how many days can they do the same work,working together?

A can do a work in 4 days while B can do that same work in 6 days. If they worked together, then that work would be completed in

A can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?

10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.

If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?

If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?

KIRAN PUBLICATION-TIME AND WORK-TEST YOURSELF
  1. A can do a piece of work in 6 days working 8 hours a day while B can d...

    Text Solution

    |

  2. A contract to be completed in 56 days and 104 men were set towork each...

    Text Solution

    |

  3. 12 men and 18 boys working 7(1)/(2) hours a day can do a work in 60 da...

    Text Solution

    |

  4. If A alone can do a work in 12 days and B alone can do it in 8 days, W...

    Text Solution

    |

  5. A and B can do a work in 8 days. B alone can do it in 24 days. In how ...

    Text Solution

    |

  6. A can do (1)/(2) of a work in 9 days while B can do (1)/(3) of the sam...

    Text Solution

    |

  7. A can do a work in 12 days and B can do it in 16 days. A and B started...

    Text Solution

    |

  8. Ram can do a piece of work in 20 days and Shyam in 30 days. They work ...

    Text Solution

    |

  9. A and B can complete a piece of work in 45 and 40 days respectively. B...

    Text Solution

    |

  10. A can do a piece of work in 40 days. He works on it for 5 days and the...

    Text Solution

    |

  11. Rita, Sita and Meeta are employed to do a piece of work for Rs 625. Ri...

    Text Solution

    |

  12. A and B can do a piece of work in 10 days, B and C in 15 days and C an...

    Text Solution

    |

  13. A, B and C can complete a work In 8 days. B alone can do it in 18 days...

    Text Solution

    |

  14. A alone takes as much time as B and C together take to complete a piec...

    Text Solution

    |

  15. A and B together can finish a work in 15 days. A and C take 2 days mor...

    Text Solution

    |

  16. A and B together can do a piece of work in 30 days, B and C together c...

    Text Solution

    |

  17. A and B can do a piece of work in 12 days, B and C in 15 days, C and A...

    Text Solution

    |

  18. A can complete a work in 24 days, B in 32 days and C in 64 days. They ...

    Text Solution

    |

  19. A, B and C can complete a work separately in 24, 36 and 48 days respec...

    Text Solution

    |

  20. A can complete a work in 10 days, B can complete the same work in 20 d...

    Text Solution

    |

  21. A can do a piece of work in 120 days and B can do it in 150 days. They...

    Text Solution

    |