8 men can do a work in 12 days. After 6 ...

8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finIsh the work. In how many days would the remaining work be completed?

A

2

B

3

C

4

D

5

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-IV|32 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?

24 men can complete a piece of work in 15 days. 2 days after the 24 men started working, 4 men left the work. How many more days will the remaining men now take to complete the remaining work?

KIRAN PUBLICATION-TIME AND WORK-TYPE-II
  1. A and B can do a piece of work in 30 days while B and C can do the sam...

    Text Solution

    |

  2. A and B can together finish a work in 30 days. They worked together fo...

    Text Solution

    |

  3. 8 men can do a work in 12 days. After 6 days of work, 4 more men were ...

    Text Solution

    |

  4. A certain number of persons can complete a piece of work in 55 days. I...

    Text Solution

    |

  5. A and B working separately can do a piece of work in 10 days and 15 da...

    Text Solution

    |

  6. A and B can do a piece of work in 20 and 25 days respectively. They be...

    Text Solution

    |

  7. A and B can do a piece of work in 20 days and 12 days respectively. A ...

    Text Solution

    |

  8. A man and a boy can complete a work together in 24 days. If for the la...

    Text Solution

    |

  9. A and B together can complete a work in 8 days . B alone can complete ...

    Text Solution

    |

  10. A, B and C can complete a work in 10, 12 and 15 days respectively. The...

    Text Solution

    |

  11. A can complete a piece of work in 10 days, B in 15 days and C in 20 da...

    Text Solution

    |

  12. 40 men can complete a work in 40 days. They started the work together....

    Text Solution

    |

  13. A and B alone can complete work in 9 days and 18 days respectively. Th...

    Text Solution

    |

  14. A can complete a piece of work In 18 days, B in 20 days and C in 30 da...

    Text Solution

    |

  15. A and B together can do a work in 12 days. A alone can do this in 20 d...

    Text Solution

    |

  16. A and B can do a piece of work in 12 days and 15 days respectively. Th...

    Text Solution

    |

  17. X alone can complete a piece of work in 40 days. He worked for 8 days...

    Text Solution

    |

  18. A, B and C can do a piece of work in 30, 20 and 10 days respectively. ...

    Text Solution

    |

  19. A can do a piece of work in 20 days which B can do in 12 days. B worke...

    Text Solution

    |

  20. A can do a piece of work in 8 days which B can destroy in 3 days. A ha...

    Text Solution

    |