A and B can do a piece of work in 20 day...

A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

A

10 days

B

20 days

C

15 days

D

6 days

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-IV|32 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last? 6 d a y s b. 10 d a y s c. 1 5 d a y s d. 20 d a y s

X and Y can do a piece of work in 20 days and 12 days respectively. X started line work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?

A and B can do a piece of work in 6 and 12 days, respectively. They (both) will complete the work in how many days?

A and B can do a piece of work in 20 days and 30 days respectively. A start the work and they do this work in alternate days. In how many days will this work be completed ?

A\ a n d\ B can do a piece of work in 6 days and 4 days respectively. A started the work; worked at it for 2 days and then was joined by B . Find the total time taken to complete the work.

A and B can do a piece of work in 20 days and 25 days. A start the work and they do this work in alternate days. In how many days will this work be completed ?

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

B is twice efficient as A and A can do a piece of work in 15 days. A started the work and after a few days B joined him. They completed the work in 11 days, from the starting. For how many days they worked together?

KIRAN PUBLICATION-TIME AND WORK-TYPE-II
  1. A and B working separately can do a piece of work in 10 days and 15 da...

    Text Solution

    |

  2. A and B can do a piece of work in 20 and 25 days respectively. They be...

    Text Solution

    |

  3. A and B can do a piece of work in 20 days and 12 days respectively. A ...

    Text Solution

    |

  4. A man and a boy can complete a work together in 24 days. If for the la...

    Text Solution

    |

  5. A and B together can complete a work in 8 days . B alone can complete ...

    Text Solution

    |

  6. A, B and C can complete a work in 10, 12 and 15 days respectively. The...

    Text Solution

    |

  7. A can complete a piece of work in 10 days, B in 15 days and C in 20 da...

    Text Solution

    |

  8. 40 men can complete a work in 40 days. They started the work together....

    Text Solution

    |

  9. A and B alone can complete work in 9 days and 18 days respectively. Th...

    Text Solution

    |

  10. A can complete a piece of work In 18 days, B in 20 days and C in 30 da...

    Text Solution

    |

  11. A and B together can do a work in 12 days. A alone can do this in 20 d...

    Text Solution

    |

  12. A and B can do a piece of work in 12 days and 15 days respectively. Th...

    Text Solution

    |

  13. X alone can complete a piece of work in 40 days. He worked for 8 days...

    Text Solution

    |

  14. A, B and C can do a piece of work in 30, 20 and 10 days respectively. ...

    Text Solution

    |

  15. A can do a piece of work in 20 days which B can do in 12 days. B worke...

    Text Solution

    |

  16. A can do a piece of work in 8 days which B can destroy in 3 days. A ha...

    Text Solution

    |

  17. A and B together can complete a work in 12 days and B and C can do it ...

    Text Solution

    |

  18. A, B and C can do a piece of work in 20, 30 and 60 days respectively. ...

    Text Solution

    |

  19. A can do a piece of work in 20 days and B in 30 days. They work togeth...

    Text Solution

    |

  20. 45 men can complete a work in 16 days. Four days after they started wo...

    Text Solution

    |