Home
Class 14
MATHS
A can complete a piece of work in 10 day...

A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed ?

A

12 days

B

10 days

C

6 days

D

8 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break down the work done by A, B, and C and how the work progresses over the days. ### Step 1: Determine the work done by A, B, and C in one day. - A can complete the work in 10 days, so in one day, A does: \[ \text{Work done by A in one day} = \frac{1}{10} \text{ of the work} \] - B can complete the work in 15 days, so in one day, B does: \[ \text{Work done by B in one day} = \frac{1}{15} \text{ of the work} \] - C can complete the work in 20 days, so in one day, C does: \[ \text{Work done by C in one day} = \frac{1}{20} \text{ of the work} \] ### Step 2: Calculate the total work done by A and C together in one day. - The combined work done by A and C in one day is: \[ \text{Work done by A and C in one day} = \frac{1}{10} + \frac{1}{20} \] To add these fractions, we find a common denominator (which is 20): \[ = \frac{2}{20} + \frac{1}{20} = \frac{3}{20} \] ### Step 3: Calculate the work done by A and C in 2 days. - In 2 days, A and C together will complete: \[ \text{Work done in 2 days} = 2 \times \frac{3}{20} = \frac{6}{20} = \frac{3}{10} \] ### Step 4: Determine the remaining work after A and C have worked for 2 days. - The total work is considered as 1 (or 100% of the work). Therefore, the remaining work after A and C have completed \(\frac{3}{10}\) of the work is: \[ \text{Remaining work} = 1 - \frac{3}{10} = \frac{7}{10} \] ### Step 5: Calculate the work done by B and C together in one day. - Now, A is replaced by B. The combined work done by B and C in one day is: \[ \text{Work done by B and C in one day} = \frac{1}{15} + \frac{1}{20} \] To add these fractions, we find a common denominator (which is 60): \[ = \frac{4}{60} + \frac{3}{60} = \frac{7}{60} \] ### Step 6: Determine how many days B and C will take to complete the remaining work. - The remaining work is \(\frac{7}{10}\). To find out how many days it will take for B and C to complete this work, we set up the equation: \[ \text{Days} = \frac{\text{Remaining work}}{\text{Work done by B and C in one day}} = \frac{\frac{7}{10}}{\frac{7}{60}} = \frac{7}{10} \times \frac{60}{7} = 6 \text{ days} \] ### Step 7: Calculate the total time taken to complete the work. - The total time taken to complete the work is the time A and C worked together plus the time B and C worked together: \[ \text{Total time} = 2 \text{ days} + 6 \text{ days} = 8 \text{ days} \] ### Final Answer: The total time taken to complete the work is **8 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-IV|32 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?

A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

A can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?

A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

A and B can do a work in 12 days .B and C in 15 days .C and A in 20 days. If A,B and C work together ,they will complete the work in :

A' can do a piece of work in 4 days and B in 12 days. In how many days can A and B together complete the same piece of work ?

A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?

KIRAN PUBLICATION-TIME AND WORK-TYPE-II
  1. A and B together can complete a work in 8 days . B alone can complete ...

    Text Solution

    |

  2. A, B and C can complete a work in 10, 12 and 15 days respectively. The...

    Text Solution

    |

  3. A can complete a piece of work in 10 days, B in 15 days and C in 20 da...

    Text Solution

    |

  4. 40 men can complete a work in 40 days. They started the work together....

    Text Solution

    |

  5. A and B alone can complete work in 9 days and 18 days respectively. Th...

    Text Solution

    |

  6. A can complete a piece of work In 18 days, B in 20 days and C in 30 da...

    Text Solution

    |

  7. A and B together can do a work in 12 days. A alone can do this in 20 d...

    Text Solution

    |

  8. A and B can do a piece of work in 12 days and 15 days respectively. Th...

    Text Solution

    |

  9. X alone can complete a piece of work in 40 days. He worked for 8 days...

    Text Solution

    |

  10. A, B and C can do a piece of work in 30, 20 and 10 days respectively. ...

    Text Solution

    |

  11. A can do a piece of work in 20 days which B can do in 12 days. B worke...

    Text Solution

    |

  12. A can do a piece of work in 8 days which B can destroy in 3 days. A ha...

    Text Solution

    |

  13. A and B together can complete a work in 12 days and B and C can do it ...

    Text Solution

    |

  14. A, B and C can do a piece of work in 20, 30 and 60 days respectively. ...

    Text Solution

    |

  15. A can do a piece of work in 20 days and B in 30 days. They work togeth...

    Text Solution

    |

  16. 45 men can complete a work in 16 days. Four days after they started wo...

    Text Solution

    |

  17. A, B and C can do a job in 6 days, 12 days and 15 days respectively. A...

    Text Solution

    |

  18. 16 women take 12 days to complete a work which can be completed by 12 ...

    Text Solution

    |

  19. A, B and C together can do a piece of work in 40 days. After working w...

    Text Solution

    |

  20. Some staff promised to do a job in 18 days, but 6 of them went on leav...

    Text Solution

    |