Home
Class 14
MATHS
A and B can do a piece of work in 12 day...

A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?

A

`(20)/(3)` days

B

`(25)/(3)` days

C

6 days

D

5 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine the work rates of A and B - A can complete the work in 12 days. Therefore, A's work rate is: \[ \text{Work rate of A} = \frac{1}{12} \text{ (work per day)} \] - B can complete the work in 15 days. Therefore, B's work rate is: \[ \text{Work rate of B} = \frac{1}{15} \text{ (work per day)} \] ### Step 2: Calculate the combined work rate of A and B - When A and B work together, their combined work rate is: \[ \text{Combined work rate} = \frac{1}{12} + \frac{1}{15} \] - To add these fractions, we need a common denominator. The least common multiple (LCM) of 12 and 15 is 60. Thus: \[ \frac{1}{12} = \frac{5}{60} \quad \text{and} \quad \frac{1}{15} = \frac{4}{60} \] - Therefore, the combined work rate is: \[ \text{Combined work rate} = \frac{5}{60} + \frac{4}{60} = \frac{9}{60} = \frac{3}{20} \] ### Step 3: Calculate the amount of work done in 4 days - In 4 days, the amount of work done by A and B together is: \[ \text{Work done in 4 days} = \text{Combined work rate} \times 4 = \frac{3}{20} \times 4 = \frac{12}{20} = \frac{3}{5} \] - To express this in terms of total work, if we consider the total work to be 60 units, then: \[ \text{Work done in 4 days} = 60 \times \frac{3}{5} = 36 \text{ units} \] ### Step 4: Calculate the remaining work - The total work is 60 units, and after 4 days, 36 units have been completed. Therefore, the remaining work is: \[ \text{Remaining work} = 60 - 36 = 24 \text{ units} \] ### Step 5: Determine how long it will take B to complete the remaining work - B's work rate is \(\frac{1}{15}\) of the work per day. Therefore, in one day, B can complete: \[ \text{Work done by B in 1 day} = \frac{1}{15} \text{ of the total work} \] - To find out how many days B needs to complete the remaining 24 units, we can set up the equation: \[ \text{Days required by B} = \frac{\text{Remaining work}}{\text{Work done by B in 1 day}} = \frac{24}{\frac{1}{15}} = 24 \times 15 = 6 \text{ days} \] ### Final Answer B will take **6 more days** to complete the remaining work. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-IV|32 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

A,B and C can do a piece of work in 15,12 and 20 days respectively.They started the work together,but C left after 2 days.In how many days will the remaining work be completed by A and B?

A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:

A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave

A and B can do a piece of work in 45 and 40 days respectively.They began the work together but A leaves after some days and B finished the remaining work in 23 days.After how many days did A leave?

KIRAN PUBLICATION-TIME AND WORK-TYPE-II
  1. A can complete a piece of work In 18 days, B in 20 days and C in 30 da...

    Text Solution

    |

  2. A and B together can do a work in 12 days. A alone can do this in 20 d...

    Text Solution

    |

  3. A and B can do a piece of work in 12 days and 15 days respectively. Th...

    Text Solution

    |

  4. X alone can complete a piece of work in 40 days. He worked for 8 days...

    Text Solution

    |

  5. A, B and C can do a piece of work in 30, 20 and 10 days respectively. ...

    Text Solution

    |

  6. A can do a piece of work in 20 days which B can do in 12 days. B worke...

    Text Solution

    |

  7. A can do a piece of work in 8 days which B can destroy in 3 days. A ha...

    Text Solution

    |

  8. A and B together can complete a work in 12 days and B and C can do it ...

    Text Solution

    |

  9. A, B and C can do a piece of work in 20, 30 and 60 days respectively. ...

    Text Solution

    |

  10. A can do a piece of work in 20 days and B in 30 days. They work togeth...

    Text Solution

    |

  11. 45 men can complete a work in 16 days. Four days after they started wo...

    Text Solution

    |

  12. A, B and C can do a job in 6 days, 12 days and 15 days respectively. A...

    Text Solution

    |

  13. 16 women take 12 days to complete a work which can be completed by 12 ...

    Text Solution

    |

  14. A, B and C together can do a piece of work in 40 days. After working w...

    Text Solution

    |

  15. Some staff promised to do a job in 18 days, but 6 of them went on leav...

    Text Solution

    |

  16. A and B can do a piece of work in 45 and 40 days repectively. They beg...

    Text Solution

    |

  17. A, B and C can do a piece of work in 24 days, 30 days and 40 days resp...

    Text Solution

    |

  18. Raja can do a piece of work in 20 days while Ramesh can finish it In 2...

    Text Solution

    |

  19. Ram and Harl can cut 12 kgs nuts in 2 days. After 5 days, Harl left th...

    Text Solution

    |

  20. A certain number of men can do a plece of work in 60 days. If there we...

    Text Solution

    |