45 men can complete a work in 16 days. F...

45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?

A

6 days

B

8 days

C

`6(2)/(3)` days

D

`7(3)/(4)` days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-IV|32 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

45 men can complete a work in 16 days.Six days after they started working,30 more men joined them.How many days will they now take to complete the remaining work?

12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?

A piec of work can be done by 12 men in 24 days. After 4days. They started the work and then 6 more men joined them. How many days will they all take to complete the remaining work ?

KIRAN PUBLICATION-TIME AND WORK-TYPE-II
  1. A, B and C can do a piece of work in 20, 30 and 60 days respectively. ...

    Text Solution

    |

  2. A can do a piece of work in 20 days and B in 30 days. They work togeth...

    Text Solution

    |

  3. 45 men can complete a work in 16 days. Four days after they started wo...

    Text Solution

    |

  4. A, B and C can do a job in 6 days, 12 days and 15 days respectively. A...

    Text Solution

    |

  5. 16 women take 12 days to complete a work which can be completed by 12 ...

    Text Solution

    |

  6. A, B and C together can do a piece of work in 40 days. After working w...

    Text Solution

    |

  7. Some staff promised to do a job in 18 days, but 6 of them went on leav...

    Text Solution

    |

  8. A and B can do a piece of work in 45 and 40 days repectively. They beg...

    Text Solution

    |

  9. A, B and C can do a piece of work in 24 days, 30 days and 40 days resp...

    Text Solution

    |

  10. Raja can do a piece of work in 20 days while Ramesh can finish it In 2...

    Text Solution

    |

  11. Ram and Harl can cut 12 kgs nuts in 2 days. After 5 days, Harl left th...

    Text Solution

    |

  12. A certain number of men can do a plece of work in 60 days. If there we...

    Text Solution

    |

  13. 15 men can finish a piece of work in 40 days. The number of days after...

    Text Solution

    |

  14. A and B together can complete a piece of work in 12 days. They worked ...

    Text Solution

    |

  15. Pramod has done (1)/(4) th of a job in 9 days, Saroj completes the re...

    Text Solution

    |

  16. A labourer can do a Job in 36 hours. After 9 hours he takes a break. W...

    Text Solution

    |

  17. A, B and C can do a job working alone in 50, 75 and 20 days respective...

    Text Solution

    |

  18. A and B can together complete a task in 18 hours. After 6 hours A leav...

    Text Solution

    |

  19. A and B together can complete a work in 10 days. They started together...

    Text Solution

    |

  20. S can do a piece of work in 80 days and T in 60 days. With the help of...

    Text Solution

    |