Some staff promised to do a job in 18 da...

Some staff promised to do a job in 18 days, but 6 of them went on leave. So the remaining men took 20 days to complete the job. How many men were there originally?

A

55

B

62

C

56

D

60

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Define the variables Let \( X \) be the original number of staff members. ### Step 2: Set up the equations The staff promised to complete the job in 18 days. Therefore, the total work done can be expressed as: \[ \text{Work} = \text{Number of persons} \times \text{Number of days} = X \times 18 \] When 6 staff members went on leave, the remaining staff is \( X - 6 \). They completed the same job in 20 days: \[ \text{Work} = (X - 6) \times 20 \] ### Step 3: Equate the two expressions for work Since the total work done is the same in both cases, we can set the two equations equal to each other: \[ X \times 18 = (X - 6) \times 20 \] ### Step 4: Expand and simplify the equation Expanding the right side: \[ 18X = 20X - 120 \] ### Step 5: Rearrange the equation Now, move all terms involving \( X \) to one side: \[ 18X - 20X = -120 \] \[ -2X = -120 \] ### Step 6: Solve for \( X \) Dividing both sides by -2: \[ X = \frac{120}{2} = 60 \] ### Conclusion Thus, the original number of staff members was \( 60 \). ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-IV|32 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?

If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?

If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?

KIRAN PUBLICATION-TIME AND WORK-TYPE-II
  1. A, B and C can do a job in 6 days, 12 days and 15 days respectively. A...

    Text Solution

    |

  2. 16 women take 12 days to complete a work which can be completed by 12 ...

    Text Solution

    |

  3. A, B and C together can do a piece of work in 40 days. After working w...

    Text Solution

    |

  4. Some staff promised to do a job in 18 days, but 6 of them went on leav...

    Text Solution

    |

  5. A and B can do a piece of work in 45 and 40 days repectively. They beg...

    Text Solution

    |

  6. A, B and C can do a piece of work in 24 days, 30 days and 40 days resp...

    Text Solution

    |

  7. Raja can do a piece of work in 20 days while Ramesh can finish it In 2...

    Text Solution

    |

  8. Ram and Harl can cut 12 kgs nuts in 2 days. After 5 days, Harl left th...

    Text Solution

    |

  9. A certain number of men can do a plece of work in 60 days. If there we...

    Text Solution

    |

  10. 15 men can finish a piece of work in 40 days. The number of days after...

    Text Solution

    |

  11. A and B together can complete a piece of work in 12 days. They worked ...

    Text Solution

    |

  12. Pramod has done (1)/(4) th of a job in 9 days, Saroj completes the re...

    Text Solution

    |

  13. A labourer can do a Job in 36 hours. After 9 hours he takes a break. W...

    Text Solution

    |

  14. A, B and C can do a job working alone in 50, 75 and 20 days respective...

    Text Solution

    |

  15. A and B can together complete a task in 18 hours. After 6 hours A leav...

    Text Solution

    |

  16. A and B together can complete a work in 10 days. They started together...

    Text Solution

    |

  17. S can do a piece of work in 80 days and T in 60 days. With the help of...

    Text Solution

    |

  18. A, B and C together can finish a task in 12 days. A is twice as produ...

    Text Solution

    |

  19. A work can be completed by 28 women in 36 days. If 4 women leave after...

    Text Solution

    |

  20. A and B together can complete a work in 20 days. They started together...

    Text Solution

    |