A man and a boy received 800 as wages for 5 days for the work they did together. The man's efficiency in the work was three times that of the boy. What are the daily wages of the boy?

A

Rs 76

B

Rs 56

C

Rs 44

D

Rs 40

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-IV|32 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-II|45 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A man and a boy received Rs.800 as wages for 5 days for the work they did together.The man's efficiency in the work was three xx that of the boy.What are the daily wages of the boy? a.Rs.40 b.Rs.44 c.Rs.56 d.Rs.76

A man and a boy received Rs.1400 as wages for 10 days for the work they did together. The man's effi-ciency in the work was six times that of the boy. What is the daily wages of the boy?

A can do a piece of work in 10 days, B in 15 days. They work together for 5 days, the rest of the work is finished by C in two more days. If they get Rs. 3000 as wages for the whole work what are the daily wages of A, B and C respectively (in Rs.):

A man can build a tank in 12 hours, After working for 6 hours, he took the help of a boy and finished the work in another in 5 hours.The time that the boy will take alone to complete the work is

KIRAN PUBLICATION-TIME AND WORK-TYPE-III
  1. A and B undertook to do a piece of work for 4500. A alone could do it ...

    Text Solution

    |

  2. If 6 persons working 8 hours a day earn 8400 per week, then 9 persons ...

    Text Solution

    |

  3. A man and a boy received 800 as wages for 5 days for the work they did...

    Text Solution

    |

  4. A, B and C completed a work costing Rs 1800. A worked for 6 days, B wo...

    Text Solution

    |

  5. A labourer was appointed by a contractor on the condition he would be ...

    Text Solution

    |

  6. If 5 men or 7 women can earn 5,250 per day, how much would 7 men and 1...

    Text Solution

    |

  7. 2 men and 1 woman together can complete a piece of work in 14 days, wh...

    Text Solution

    |

  8. If there is a reduction in the number of workers in a factory in the r...

    Text Solution

    |

  9. A sum of money is sufficient to pay A's wages for 21 days and B's wage...

    Text Solution

    |

  10. Three persons undertake to complete a piece of work for ₹ 1,200. The ...

    Text Solution

    |

  11. A skilled, a half skilled and an unskilled labour work for 7, 8 and 10...

    Text Solution

    |

  12. A, B and C are employed to do a plece of work for Rs 575. A and C are...

    Text Solution

    |

  13. If a man earns ₹ 2,000 for his first 50 hours of work in a week and t...

    Text Solution

    |

  14. The daily wages of A and B respectively are ₹.3.50 and 2.50. When A fi...

    Text Solution

    |

  15. A certain factory employed 600 men and 400 women and the average wage ...

    Text Solution

    |

  16. P, Q and R can do a piece of work in 60 days, 100 days and 80 days res...

    Text Solution

    |

  17. S, T and U can complete a work In 40, 48 and 60 days respectively. The...

    Text Solution

    |

  18. Sandy and Mandy do ((8)/(13)) th part of a work and the rest of the wo...

    Text Solution

    |

  19. X and Y can complete a piece of work in 12 and 60 days respectively. T...

    Text Solution

    |

  20. Working alone A can do the task in 27 hours and B can do it in 54 hour...

    Text Solution

    |