A, B and C completed a work costing Rs 1...

A, B and C completed a work costing Rs 1800. A worked for 6 days, B worked for 4 days and C worked for 9 days. If their daily wages are in the ratio of 5:6:4, how much amount will be received by A.

A

Rs 800

B

Rs 600

C

Rs 900

D

Rs 750

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-IV|32 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-II|45 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A,B and C completes a piece of work costing Rs.1800. A worked for 6 days,B for 4 days and C for 9 days.If their daily wages are in the ratio 5:6:4, how much amount will be recieved by A.

A can do a piece of work in 9 days and B can do the same work in 15 days. If they work together, in what ratio A and B will receive their wages?

(A + B) can do a piece of work in 12 days. (B + C) can do same work in 6(2)/(3) days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days.A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?

KIRAN PUBLICATION-TIME AND WORK-TYPE-III
  1. If 6 persons working 8 hours a day earn 8400 per week, then 9 persons ...

    Text Solution

    |

  2. A man and a boy received 800 as wages for 5 days for the work they did...

    Text Solution

    |

  3. A, B and C completed a work costing Rs 1800. A worked for 6 days, B wo...

    Text Solution

    |

  4. A labourer was appointed by a contractor on the condition he would be ...

    Text Solution

    |

  5. If 5 men or 7 women can earn 5,250 per day, how much would 7 men and 1...

    Text Solution

    |

  6. 2 men and 1 woman together can complete a piece of work in 14 days, wh...

    Text Solution

    |

  7. If there is a reduction in the number of workers in a factory in the r...

    Text Solution

    |

  8. A sum of money is sufficient to pay A's wages for 21 days and B's wage...

    Text Solution

    |

  9. Three persons undertake to complete a piece of work for ₹ 1,200. The ...

    Text Solution

    |

  10. A skilled, a half skilled and an unskilled labour work for 7, 8 and 10...

    Text Solution

    |

  11. A, B and C are employed to do a plece of work for Rs 575. A and C are...

    Text Solution

    |

  12. If a man earns ₹ 2,000 for his first 50 hours of work in a week and t...

    Text Solution

    |

  13. The daily wages of A and B respectively are ₹.3.50 and 2.50. When A fi...

    Text Solution

    |

  14. A certain factory employed 600 men and 400 women and the average wage ...

    Text Solution

    |

  15. P, Q and R can do a piece of work in 60 days, 100 days and 80 days res...

    Text Solution

    |

  16. S, T and U can complete a work In 40, 48 and 60 days respectively. The...

    Text Solution

    |

  17. Sandy and Mandy do ((8)/(13)) th part of a work and the rest of the wo...

    Text Solution

    |

  18. X and Y can complete a piece of work in 12 and 60 days respectively. T...

    Text Solution

    |

  19. Working alone A can do the task in 27 hours and B can do it in 54 hour...

    Text Solution

    |

  20. If A had worked alone he would have taken 63 hours to do the task. Wha...

    Text Solution

    |