2 men and 1 woman together can complete ...

2 men and 1 woman together can complete a piece of work in 14 days, while 4 women and 2 men together can do it in 8 days. If a man gets ₹ 600 per day. how much should a woman get per day?

A

Rs 400

B

Rs 450

C

Rs 480

D

Rs 360

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-IV|32 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-II|45 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

2 men and 1 women can complete a piece of work in 14 days, while 4 women and 2 men can do the same work in 8 days . If a man gets Rs. 90 per day , what should be the wages per day of a woman ?

2 men and 1 woman can do a piece of work in 14 days, while 4 women and 2 men can do the same work in 8 days. If a man gets Rs. 90 per day, what should be the wages per day of a women?

4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?

1 man and 1 woman together can complete a piece of work in 8 days. A man alone can complete the work in 10 days. In how many days, can one woman alone complete the work?

2 men and 3 women can do a piece of work in 10 days, while 3 men nd 2 women can do the same work in 8 days. Then, 2 men and 1 woman can do the same work in

2 men and 7 women can do a piece of work in 14 days whereas 3 men and 8 women can do it in 11 days. In how many days 5 men and 4 women can do the same work?

4men and 6 women can complete a work in 8 days,While 3 men and 7 women can complete it in 10 days.In how many days will 10 women complete it.

KIRAN PUBLICATION-TIME AND WORK-TYPE-III
  1. A labourer was appointed by a contractor on the condition he would be ...

    Text Solution

    |

  2. If 5 men or 7 women can earn 5,250 per day, how much would 7 men and 1...

    Text Solution

    |

  3. 2 men and 1 woman together can complete a piece of work in 14 days, wh...

    Text Solution

    |

  4. If there is a reduction in the number of workers in a factory in the r...

    Text Solution

    |

  5. A sum of money is sufficient to pay A's wages for 21 days and B's wage...

    Text Solution

    |

  6. Three persons undertake to complete a piece of work for ₹ 1,200. The ...

    Text Solution

    |

  7. A skilled, a half skilled and an unskilled labour work for 7, 8 and 10...

    Text Solution

    |

  8. A, B and C are employed to do a plece of work for Rs 575. A and C are...

    Text Solution

    |

  9. If a man earns ₹ 2,000 for his first 50 hours of work in a week and t...

    Text Solution

    |

  10. The daily wages of A and B respectively are ₹.3.50 and 2.50. When A fi...

    Text Solution

    |

  11. A certain factory employed 600 men and 400 women and the average wage ...

    Text Solution

    |

  12. P, Q and R can do a piece of work in 60 days, 100 days and 80 days res...

    Text Solution

    |

  13. S, T and U can complete a work In 40, 48 and 60 days respectively. The...

    Text Solution

    |

  14. Sandy and Mandy do ((8)/(13)) th part of a work and the rest of the wo...

    Text Solution

    |

  15. X and Y can complete a piece of work in 12 and 60 days respectively. T...

    Text Solution

    |

  16. Working alone A can do the task in 27 hours and B can do it in 54 hour...

    Text Solution

    |

  17. If A had worked alone he would have taken 63 hours to do the task. Wha...

    Text Solution

    |

  18. P alone can complete the work in 5 days,Q alone can do same work in 6 ...

    Text Solution

    |

  19. A and B undertook a work for Rs. 2200. A alone can do the work in 10 d...

    Text Solution

    |

  20. Ram and Shyam undertook a work for Rs. 5600. Ram alone can do the work...

    Text Solution

    |