Kamal can do a work in 15 days. Bimal is...

Kamal can do a work in 15 days. Bimal is 50 per cent more efficient than Kamal in doing the work. In how many days will Bimal do that work?

A

A) 14 days

B

B) 12 days

C

C) 10 days

D

D) `10(1)/(2)` days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-VI|59 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in

Kamal can do a work n15 days.Bimal is 50% more efficient than Kamal.The number of days,Bimal will take to do the same piece of work is 7(1)/(2) b.10 c.14 d.12

Vivek can do a certain work in 14 days. Vishal is 75% more efficient than Vivek. How many days will Vishal alone take to do the same work?

A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?

KIRAN PUBLICATION-TIME AND WORK-TYPE-IV
  1. A and B together can do a work in 12 days. B and C together do It in 1...

    Text Solution

    |

  2. A does half as much work as B and C does half as much work as A and B ...

    Text Solution

    |

  3. Kamal can do a work in 15 days. Bimal is 50 per cent more efficient th...

    Text Solution

    |

  4. X takes 10 days less than the time taken by Y to finish a piece of wor...

    Text Solution

    |

  5. 5 men and 2 women working together can do four times as much work per ...

    Text Solution

    |

  6. P is thrice as good a workman as Q and therefore able to finish a Job ...

    Text Solution

    |

  7. To do a certain work, B would take time thrice as long as A and C toge...

    Text Solution

    |

  8. Two workers A and B working together completed a job in 5 days. If A w...

    Text Solution

    |

  9. Sunil completes a work in 4 days, whereas Dinesh completes the work in...

    Text Solution

    |

  10. A man does double the work done by a boy in the same time. The number ...

    Text Solution

    |

  11. If 10 people can do a job in 20 days, then 20 people with twice the ef...

    Text Solution

    |

  12. Manoj can do a piece of work in 42 hours. If he is joined by Jayshree ...

    Text Solution

    |

  13. A is 1.5 times efficient than B therefore takes 8 days less than B to ...

    Text Solution

    |

  14. Working together, X and Y can do a piece of work in 12 days, Y and Z ...

    Text Solution

    |

  15. A is 20% more efficient than B.B can do a piece of work in 20 days. In...

    Text Solution

    |

  16. P is 20% more efficient than Q. If Q alone can finish a work in 10 day...

    Text Solution

    |

  17. S, T and U together can complete a work in 30 days. If the ratio of ef...

    Text Solution

    |

  18. C is 5 times as productive as B. A takes 60 days to complete a task. ...

    Text Solution

    |

  19. A can complete 50% of a job in 9 days and B can complete 25% of the jo...

    Text Solution

    |

  20. A, B and C together can complete a work in 25 days. If the ratio of ef...

    Text Solution

    |