Home
Class 14
MATHS
A is 1.5 times efficient than B therefor...

A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

A

17

B

19

C

19.5

D

21

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will break it down into manageable parts. ### Step 1: Determine the time taken by A and B to complete the work. Let the time taken by B to complete the work be \( x \) days. Since A is 1.5 times more efficient than B, the time taken by A to complete the work will be \( \frac{x}{1.5} = \frac{2x}{3} \). According to the problem, A takes 8 days less than B to complete the work: \[ \frac{2x}{3} = x - 8 \] ### Step 2: Solve the equation for \( x \). To eliminate the fraction, multiply the entire equation by 3: \[ 2x = 3x - 24 \] Rearranging gives: \[ 3x - 2x = 24 \implies x = 24 \] ### Step 3: Calculate the time taken by A. Now that we have \( x = 24 \), we can find the time taken by A: \[ \text{Time taken by A} = \frac{2x}{3} = \frac{2 \times 24}{3} = 16 \text{ days} \] ### Step 4: Determine the work done by A and B in one day. The work done by A in one day is: \[ \text{Work done by A in one day} = \frac{1}{16} \] The work done by B in one day is: \[ \text{Work done by B in one day} = \frac{1}{24} \] ### Step 5: Calculate the total work done in two days. Since A and B work on alternate days, we can calculate the work done in 2 days (A works on the first day and B on the second day): \[ \text{Work done in 2 days} = \frac{1}{16} + \frac{1}{24} \] To add these fractions, find a common denominator (which is 48): \[ \frac{1}{16} = \frac{3}{48}, \quad \frac{1}{24} = \frac{2}{48} \] Thus, \[ \text{Work done in 2 days} = \frac{3}{48} + \frac{2}{48} = \frac{5}{48} \] ### Step 6: Calculate the total number of days required to complete the work. Let \( W \) be the total work, which we can consider as 1 unit of work. The number of 2-day cycles needed to complete the work is: \[ \text{Number of 2-day cycles} = \frac{1}{\frac{5}{48}} = \frac{48}{5} = 9.6 \text{ cycles} \] This means it will take 9 complete cycles (18 days) and a fraction of a cycle to complete the work. ### Step 7: Calculate the remaining work after 9 cycles. After 9 cycles (18 days), the work done is: \[ \text{Work done in 18 days} = 9 \times \frac{5}{48} = \frac{45}{48} \] The remaining work is: \[ 1 - \frac{45}{48} = \frac{3}{48} = \frac{1}{16} \] ### Step 8: Determine how long it will take to finish the remaining work. Since A works on the first day of the next cycle, A will complete the remaining work of \( \frac{1}{16} \) in 1 day. ### Final Calculation: Total days taken. Thus, the total days taken to complete the work is: \[ \text{Total days} = 18 + 1 = 19 \text{ days} \] ### Conclusion: The work will be completed in **19 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-VI|59 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A is twice as good a workman as B and therefore A takes 6 days less than B to finish the work individually. If A and B working complete together the work in 4 days, then how many days are required by B to complete the work alone?

If man A complete a work in 10 days & man B complete the same work in 15 days , in how many days the work is completed if they work together ?

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

KIRAN PUBLICATION-TIME AND WORK-TYPE-IV
  1. To do a certain work, B would take time thrice as long as A and C toge...

    Text Solution

    |

  2. Two workers A and B working together completed a job in 5 days. If A w...

    Text Solution

    |

  3. Sunil completes a work in 4 days, whereas Dinesh completes the work in...

    Text Solution

    |

  4. A man does double the work done by a boy in the same time. The number ...

    Text Solution

    |

  5. If 10 people can do a job in 20 days, then 20 people with twice the ef...

    Text Solution

    |

  6. Manoj can do a piece of work in 42 hours. If he is joined by Jayshree ...

    Text Solution

    |

  7. A is 1.5 times efficient than B therefore takes 8 days less than B to ...

    Text Solution

    |

  8. Working together, X and Y can do a piece of work in 12 days, Y and Z ...

    Text Solution

    |

  9. A is 20% more efficient than B.B can do a piece of work in 20 days. In...

    Text Solution

    |

  10. P is 20% more efficient than Q. If Q alone can finish a work in 10 day...

    Text Solution

    |

  11. S, T and U together can complete a work in 30 days. If the ratio of ef...

    Text Solution

    |

  12. C is 5 times as productive as B. A takes 60 days to complete a task. ...

    Text Solution

    |

  13. A can complete 50% of a job in 9 days and B can complete 25% of the jo...

    Text Solution

    |

  14. A, B and C together can complete a work in 25 days. If the ratio of ef...

    Text Solution

    |

  15. R is 80% more efficient than S. If S alone can make a book in 90 days,...

    Text Solution

    |

  16. To complete a wall, X takes 20% more time than Y. If together they com...

    Text Solution

    |

  17. Mohit is five times more efficient as Rohit. If Mohit can complete a p...

    Text Solution

    |

  18. Rama and Hari together can do a work in 15 days. Rama is twice as effi...

    Text Solution

    |

  19. The efficiencies of A, B and C are in the ratio 2 : 5 : 7 working toge...

    Text Solution

    |

  20. The ratio of the efficiencies of A, B and C is 2 : 5 : 3. Working toge...

    Text Solution

    |