Working together, X and Y can do a piece...

Working together, X and Y can do a piece of work in 12 days, Y and Z can do it in 15 days where as X and Z can do it in 20 days. Who is the most effcient?

A

X

B

Y

C

Z

D

Cannot be determined

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-VI|59 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:

X and Y can do a piece of work in 72 days. Y and Z can do it in 120 days. X and Z can do it in 90 days. In how many days all the three together can do the work ? A)100 days B)150 days C)60 days D) 80 days

A and B together can do a piece of work in 12 days and A alone can do it in 18 days. In how many days canBalone do it?

A and B together can do a piece of work in 12 days; B and C can do it in 20 days while C and A can do it in 15 days. A, B and C all working together can do it in

A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days they can complete the work, working together?

KIRAN PUBLICATION-TIME AND WORK-TYPE-IV
  1. To do a certain work, B would take time thrice as long as A and C toge...

    Text Solution

    |

  2. Two workers A and B working together completed a job in 5 days. If A w...

    Text Solution

    |

  3. Sunil completes a work in 4 days, whereas Dinesh completes the work in...

    Text Solution

    |

  4. A man does double the work done by a boy in the same time. The number ...

    Text Solution

    |

  5. If 10 people can do a job in 20 days, then 20 people with twice the ef...

    Text Solution

    |

  6. Manoj can do a piece of work in 42 hours. If he is joined by Jayshree ...

    Text Solution

    |

  7. A is 1.5 times efficient than B therefore takes 8 days less than B to ...

    Text Solution

    |

  8. Working together, X and Y can do a piece of work in 12 days, Y and Z ...

    Text Solution

    |

  9. A is 20% more efficient than B.B can do a piece of work in 20 days. In...

    Text Solution

    |

  10. P is 20% more efficient than Q. If Q alone can finish a work in 10 day...

    Text Solution

    |

  11. S, T and U together can complete a work in 30 days. If the ratio of ef...

    Text Solution

    |

  12. C is 5 times as productive as B. A takes 60 days to complete a task. ...

    Text Solution

    |

  13. A can complete 50% of a job in 9 days and B can complete 25% of the jo...

    Text Solution

    |

  14. A, B and C together can complete a work in 25 days. If the ratio of ef...

    Text Solution

    |

  15. R is 80% more efficient than S. If S alone can make a book in 90 days,...

    Text Solution

    |

  16. To complete a wall, X takes 20% more time than Y. If together they com...

    Text Solution

    |

  17. Mohit is five times more efficient as Rohit. If Mohit can complete a p...

    Text Solution

    |

  18. Rama and Hari together can do a work in 15 days. Rama is twice as effi...

    Text Solution

    |

  19. The efficiencies of A, B and C are in the ratio 2 : 5 : 7 working toge...

    Text Solution

    |

  20. The ratio of the efficiencies of A, B and C is 2 : 5 : 3. Working toge...

    Text Solution

    |