A is 20% more efficient than B.B can do ...

A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?

A

10

B

12

C

14

D

16

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-VI|59 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-III|31 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 16 days and B can do the same work in 20 days.In how many days can they do the same work,working together?

A is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?

A can do (1)/(10) th of a piece of work in a day. B can do the same work in 15 days. In how many days can they do the same work, working together?

A can do (1)/(4) th of a piece of work in one day. While B can do (1)/(6) th of the work in a day. In how many days can they do the same work, working together?

KIRAN PUBLICATION-TIME AND WORK-TYPE-IV
  1. To do a certain work, B would take time thrice as long as A and C toge...

    Text Solution

    |

  2. Two workers A and B working together completed a job in 5 days. If A w...

    Text Solution

    |

  3. Sunil completes a work in 4 days, whereas Dinesh completes the work in...

    Text Solution

    |

  4. A man does double the work done by a boy in the same time. The number ...

    Text Solution

    |

  5. If 10 people can do a job in 20 days, then 20 people with twice the ef...

    Text Solution

    |

  6. Manoj can do a piece of work in 42 hours. If he is joined by Jayshree ...

    Text Solution

    |

  7. A is 1.5 times efficient than B therefore takes 8 days less than B to ...

    Text Solution

    |

  8. Working together, X and Y can do a piece of work in 12 days, Y and Z ...

    Text Solution

    |

  9. A is 20% more efficient than B.B can do a piece of work in 20 days. In...

    Text Solution

    |

  10. P is 20% more efficient than Q. If Q alone can finish a work in 10 day...

    Text Solution

    |

  11. S, T and U together can complete a work in 30 days. If the ratio of ef...

    Text Solution

    |

  12. C is 5 times as productive as B. A takes 60 days to complete a task. ...

    Text Solution

    |

  13. A can complete 50% of a job in 9 days and B can complete 25% of the jo...

    Text Solution

    |

  14. A, B and C together can complete a work in 25 days. If the ratio of ef...

    Text Solution

    |

  15. R is 80% more efficient than S. If S alone can make a book in 90 days,...

    Text Solution

    |

  16. To complete a wall, X takes 20% more time than Y. If together they com...

    Text Solution

    |

  17. Mohit is five times more efficient as Rohit. If Mohit can complete a p...

    Text Solution

    |

  18. Rama and Hari together can do a work in 15 days. Rama is twice as effi...

    Text Solution

    |

  19. The efficiencies of A, B and C are in the ratio 2 : 5 : 7 working toge...

    Text Solution

    |

  20. The ratio of the efficiencies of A, B and C is 2 : 5 : 3. Working toge...

    Text Solution

    |