A can do a piece of work in 60 days. He ...

A can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in

A

24 days

B

25 days

C

30 days

D

32 days

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?

A can do a piece of work in 80 days.He works at it for 10 days and then B alore finishes the remaining work in 42 days.How long will B take to do the entire work alone?

A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

X and Y can do a piece of work in 30 days. They work together for 6 days and thenX quits and Y finishes the work in 32 days . In how many days can Y do the piece of work alone ?

KIRAN PUBLICATION-TIME AND WORK-TYPE-VI
  1. A certain number of men can complete a job in 30 days. If there were 5...

    Text Solution

    |

  2. If the expenditure of gas on burning 6 burners for 6 hours a day for 8...

    Text Solution

    |

  3. A can do a piece of work in 60 days. He works for 15 days and then B a...

    Text Solution

    |

  4. A can do a certain work in the same time in which B and C together can...

    Text Solution

    |

  5. 12 persons can do a piece of work in 4 days. How many persons are requ...

    Text Solution

    |

  6. A work could be completed in 100 days by some workers. However, due to...

    Text Solution

    |

  7. A job can be completed by 12 men in 12 days. How many extra days will ...

    Text Solution

    |

  8. 60 men could complete a work in 250 days. They worked together for 200...

    Text Solution

    |

  9. Working 5 hours a day. A can complete a work in 8 days and working 6 h...

    Text Solution

    |

  10. If two persons, with equal abilities, can do two jobs in two days, the...

    Text Solution

    |

  11. Ganga and Saraswati, working separately can mow a fleld in 8 and 12 ho...

    Text Solution

    |

  12. A road of 5 km length will be con structed in 100 days. So 280 workers...

    Text Solution

    |

  13. Working efficiencies of P and Q for completing a piece of work are in ...

    Text Solution

    |

  14. Twenty women together complete a piece of work in 16 days, 16 men toge...

    Text Solution

    |

  15. A man and a woman working together can do a certain work in 18 days. T...

    Text Solution

    |

  16. Two men can do a piece of work in x days. But y women can do that in 3...

    Text Solution

    |

  17. A farmer can plough a field working 6 hours per day in 18 days. The wo...

    Text Solution

    |

  18. If 12 carpenters working 6 hours a day can make 460 chairs in 240 days...

    Text Solution

    |

  19. 8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 da...

    Text Solution

    |

  20. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |