60 men could complete a work in 250 days...

60 men could complete a work in 250 days. They worked together for 200 days. After that the work had to be stopped for 10 days due to bad weather. How many more men should be engaged to complete the work in time?

A

10

B

15

C

18

D

20

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when. After 4 days 5 men left the work .

If 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?

15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when. After 4 days 5 more men join the work.

Twenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?

24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?

20 men can do a work in 35 days. How many men are needed to complete the same work in 25 days.

KIRAN PUBLICATION-TIME AND WORK-TYPE-VI
  1. A work could be completed in 100 days by some workers. However, due to...

    Text Solution

    |

  2. A job can be completed by 12 men in 12 days. How many extra days will ...

    Text Solution

    |

  3. 60 men could complete a work in 250 days. They worked together for 200...

    Text Solution

    |

  4. Working 5 hours a day. A can complete a work in 8 days and working 6 h...

    Text Solution

    |

  5. If two persons, with equal abilities, can do two jobs in two days, the...

    Text Solution

    |

  6. Ganga and Saraswati, working separately can mow a fleld in 8 and 12 ho...

    Text Solution

    |

  7. A road of 5 km length will be con structed in 100 days. So 280 workers...

    Text Solution

    |

  8. Working efficiencies of P and Q for completing a piece of work are in ...

    Text Solution

    |

  9. Twenty women together complete a piece of work in 16 days, 16 men toge...

    Text Solution

    |

  10. A man and a woman working together can do a certain work in 18 days. T...

    Text Solution

    |

  11. Two men can do a piece of work in x days. But y women can do that in 3...

    Text Solution

    |

  12. A farmer can plough a field working 6 hours per day in 18 days. The wo...

    Text Solution

    |

  13. If 12 carpenters working 6 hours a day can make 460 chairs in 240 days...

    Text Solution

    |

  14. 8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 da...

    Text Solution

    |

  15. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |

  16. Work done by (x+4) men in (x+5) days is equal to the work done by (x-...

    Text Solution

    |

  17. A group of workers can complete a piece of work in 50 days, when they ...

    Text Solution

    |

  18. A canteen requires 56 kgs of rice for seven days. The quantity of rice...

    Text Solution

    |

  19. A school has 8 periods of 45 min each, everyday. How long will each p...

    Text Solution

    |

  20. If 7 spiders make 7 webs in 7 days, then 1 spider will make 1 web in h...

    Text Solution

    |