A road of 5 km length will be con struct...

A road of 5 km length will be con structed in 100 days. So 280 workers were employed. But after 80 days it was found that only `3(1)/(2)` km road was completed. Now how many more people were needed to finish the work in the specified time?

A

480

B

80

C

200

D

100

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will break down the information given and calculate how many more workers are needed to complete the road construction on time. ### Step 1: Understand the problem - A road of length 5 km is to be constructed in 100 days. - 280 workers are employed for this task. - After 80 days, only 3.5 km of the road has been completed. ### Step 2: Calculate the amount of work completed - Total work required = 5 km - Work completed in 80 days = 3.5 km - Work remaining = Total work - Work completed = 5 km - 3.5 km = 1.5 km ### Step 3: Determine the remaining time - Total time for construction = 100 days - Time spent = 80 days - Remaining time = Total time - Time spent = 100 days - 80 days = 20 days ### Step 4: Calculate the work done per day by the current workers - Work done by 280 workers in 80 days = 3.5 km - Work done per day = Total work done / Number of days = 3.5 km / 80 days = 0.04375 km/day ### Step 5: Calculate the total work rate needed to finish the remaining work - Remaining work = 1.5 km - Time left = 20 days - Required work rate to finish on time = Remaining work / Remaining time = 1.5 km / 20 days = 0.075 km/day ### Step 6: Calculate the number of workers needed to achieve the required work rate - Current work rate of 280 workers = 0.04375 km/day - Work rate per worker = 0.04375 km/day / 280 workers = 0.00015625 km/worker/day - Required number of workers = Required work rate / Work rate per worker = 0.075 km/day / 0.00015625 km/worker/day ### Step 7: Calculate the required number of workers - Required number of workers = 0.075 / 0.00015625 = 480 workers ### Step 8: Calculate how many more workers are needed - Current number of workers = 280 - Additional workers needed = Required workers - Current workers = 480 - 280 = 200 workers ### Final Answer 200 more workers are needed to finish the work in the specified time. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in time?

90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?

A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extre men should he employ so that the work is completed on time?

A contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?

A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

20 persons completed 1/3 rd of the work in 12 days. How many more person are required to finish rest work in next 12 days?

A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time

20 persons completed (1)/(3)rd of the work in 24 days. How many more person are required to finish the rest of the work in next 12 days?

A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that (1)/(3)rd of the work was still to be done. How many more men were required to complete the work in stipulated time?

KIRAN PUBLICATION-TIME AND WORK-TYPE-VI
  1. If two persons, with equal abilities, can do two jobs in two days, the...

    Text Solution

    |

  2. Ganga and Saraswati, working separately can mow a fleld in 8 and 12 ho...

    Text Solution

    |

  3. A road of 5 km length will be con structed in 100 days. So 280 workers...

    Text Solution

    |

  4. Working efficiencies of P and Q for completing a piece of work are in ...

    Text Solution

    |

  5. Twenty women together complete a piece of work in 16 days, 16 men toge...

    Text Solution

    |

  6. A man and a woman working together can do a certain work in 18 days. T...

    Text Solution

    |

  7. Two men can do a piece of work in x days. But y women can do that in 3...

    Text Solution

    |

  8. A farmer can plough a field working 6 hours per day in 18 days. The wo...

    Text Solution

    |

  9. If 12 carpenters working 6 hours a day can make 460 chairs in 240 days...

    Text Solution

    |

  10. 8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 da...

    Text Solution

    |

  11. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |

  12. Work done by (x+4) men in (x+5) days is equal to the work done by (x-...

    Text Solution

    |

  13. A group of workers can complete a piece of work in 50 days, when they ...

    Text Solution

    |

  14. A canteen requires 56 kgs of rice for seven days. The quantity of rice...

    Text Solution

    |

  15. A school has 8 periods of 45 min each, everyday. How long will each p...

    Text Solution

    |

  16. If 7 spiders make 7 webs in 7 days, then 1 spider will make 1 web in h...

    Text Solution

    |

  17. Sister can bake 50 cakes in 25 hours, Sister and Mummy together can ba...

    Text Solution

    |

  18. A can do a work in 15 days and B in 20 days.If they together work on i...

    Text Solution

    |

  19. A can complete a piece of work in 18 days and B can complete the same ...

    Text Solution

    |

  20. A does (7)/(10) part of work in 15 days. After that he completes the r...

    Text Solution

    |