Home
Class 14
MATHS
8 workers can build a wall 18 m long, 2 ...

8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 days, working 9 hours a day. Find how many workers will be able to build a wall 32 m long, 3 m broad and 9 m high in 8 days working 6 hours a day?

A

16

B

20

C

30

D

10

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first calculate the volume of the wall that the first set of workers can build, and then use that information to find out how many workers are needed for the second wall. ### Step 1: Calculate the volume of the first wall The volume of a wall can be calculated using the formula: \[ \text{Volume} = \text{Length} \times \text{Breadth} \times \text{Height} \] For the first wall: - Length = 18 m - Breadth = 2 m - Height = 12 m So, the volume of the first wall is: \[ \text{Volume} = 18 \, \text{m} \times 2 \, \text{m} \times 12 \, \text{m} = 432 \, \text{m}^3 \] ### Step 2: Calculate the total work done by the workers The total work done by the workers can be calculated in terms of worker-hours. Given: - Number of workers = 8 - Hours worked per day = 9 - Days worked = 10 Total work done (in worker-hours) is: \[ \text{Total Work} = \text{Number of Workers} \times \text{Hours per Day} \times \text{Days} \] \[ \text{Total Work} = 8 \times 9 \times 10 = 720 \, \text{worker-hours} \] ### Step 3: Calculate the work required to build the wall The work required to build the first wall can be expressed as: \[ \text{Work Required} = \text{Volume of Wall} \] We know that 720 worker-hours are required to build 432 m³ of wall. Therefore, the work required per cubic meter is: \[ \text{Work per m}^3 = \frac{720 \, \text{worker-hours}}{432 \, \text{m}^3} = \frac{720}{432} = \frac{5}{3} \, \text{worker-hours/m}^3 \] ### Step 4: Calculate the volume of the second wall Now, we need to calculate the volume of the second wall: - Length = 32 m - Breadth = 3 m - Height = 9 m So, the volume of the second wall is: \[ \text{Volume} = 32 \, \text{m} \times 3 \, \text{m} \times 9 \, \text{m} = 864 \, \text{m}^3 \] ### Step 5: Calculate the total work required for the second wall Using the work per cubic meter calculated earlier, the total work required for the second wall is: \[ \text{Total Work Required} = \text{Volume of Second Wall} \times \text{Work per m}^3 \] \[ \text{Total Work Required} = 864 \, \text{m}^3 \times \frac{5}{3} \, \text{worker-hours/m}^3 = 1440 \, \text{worker-hours} \] ### Step 6: Calculate the number of workers needed Now we need to find out how many workers are required to complete this work in the given time. Given: - Days = 8 - Hours per Day = 6 Total available worker-hours with \( x \) workers is: \[ \text{Total Worker-Hours} = x \times 6 \times 8 = 48x \] Setting this equal to the total work required: \[ 48x = 1440 \] Now, solving for \( x \): \[ x = \frac{1440}{48} = 30 \] ### Final Answer Thus, **30 workers** will be able to build the second wall in the given time. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

It is given that 16men working 18hr per day can build a wall 36m long, 4m broad and 24m high in 20 days . How many men will be required to build a wall 64 m long 6m broad and 18m high working 12hr per day in 16 days ?

Find the surface area of a cuboid 10 m long, 5 m broad and 3 m high.

40 men can build a wall 200 m long in 12 days, working 8 h a day. What will be the number of days that 30 men will take to build a similar wall 300 m long, working 6 h per day

If 17 labourers can dig a ditch 20 m long in 18 days working 8 hours a day; how many more labourers should be engaged to dig a similar ditch 39 m long in 6 day, each labourer working 9 hours a day? 34 b. 51 c. 68 d. 85

Find the volume and surface area of a cuboid 18 m long, 14 m broad and 7 m high.

40 men can build a wall 200 m longin 12 days working 8 h a day. The number of days 30 men will take to build a similar wall 300 m long working 6h per day will be (A) 32 (B) 18 (C) 36 (D) 9

A tank is 8m long,6m broad and 2m high.How much water can it contain?

Find the length of the longest pole that can be placed in a room 30 m long, 24 m broad and 18 m high .

KIRAN PUBLICATION-TIME AND WORK-TYPE-VI
  1. A farmer can plough a field working 6 hours per day in 18 days. The wo...

    Text Solution

    |

  2. If 12 carpenters working 6 hours a day can make 460 chairs in 240 days...

    Text Solution

    |

  3. 8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 da...

    Text Solution

    |

  4. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |

  5. Work done by (x+4) men in (x+5) days is equal to the work done by (x-...

    Text Solution

    |

  6. A group of workers can complete a piece of work in 50 days, when they ...

    Text Solution

    |

  7. A canteen requires 56 kgs of rice for seven days. The quantity of rice...

    Text Solution

    |

  8. A school has 8 periods of 45 min each, everyday. How long will each p...

    Text Solution

    |

  9. If 7 spiders make 7 webs in 7 days, then 1 spider will make 1 web in h...

    Text Solution

    |

  10. Sister can bake 50 cakes in 25 hours, Sister and Mummy together can ba...

    Text Solution

    |

  11. A can do a work in 15 days and B in 20 days.If they together work on i...

    Text Solution

    |

  12. A can complete a piece of work in 18 days and B can complete the same ...

    Text Solution

    |

  13. A does (7)/(10) part of work in 15 days. After that he completes the r...

    Text Solution

    |

  14. A can do (1)/(2) of a piece of work in 5 days B can do (3)/(5) of the ...

    Text Solution

    |

  15. If 28 men complete (7)/(8) of a plece of work in a week, then the numb...

    Text Solution

    |

  16. P can complete (1)/(3) of a work in 10 days, Q can complete 40% of the...

    Text Solution

    |

  17. A alone can do a plece of work in 20 days and B alone in 30 days. They...

    Text Solution

    |

  18. A does half as much work as B in three fourth of the times. If togethe...

    Text Solution

    |

  19. A can do one and a half as much of a work which B can do in one day. B...

    Text Solution

    |

  20. Two workers A and B are engaged to do a piece of work. A working alone...

    Text Solution

    |