P and Q together can do a job in 6 days....

P and Q together can do a job in 6 days. Q and R can finish the same job in `(60)/(7)` days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.

A

15

B

10

C

8

D

12

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

X and Y together can finish a job in 6 days. X can alone do the same job in 12 days. How long will Y alone take to do the same job ?

P can do a job in 12 days and Q can do the same job in 6 days, in how many days working together they can complete the job?

A can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?

A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?

P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

A can do a job in 16 days and B can do the same job in 12 days. With the help of C, they can finish the job in 6 days only. Then, C alone can finish it in

P and Q can do a job in 2 days, Q and R can do it in 4 days, and P and R in 12/5 days. What is the number of days required for P alone to do the job?

KIRAN PUBLICATION-TIME AND WORK-TYPE-VI
  1. If 12 carpenters working 6 hours a day can make 460 chairs in 240 days...

    Text Solution

    |

  2. 8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 da...

    Text Solution

    |

  3. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |

  4. Work done by (x+4) men in (x+5) days is equal to the work done by (x-...

    Text Solution

    |

  5. A group of workers can complete a piece of work in 50 days, when they ...

    Text Solution

    |

  6. A canteen requires 56 kgs of rice for seven days. The quantity of rice...

    Text Solution

    |

  7. A school has 8 periods of 45 min each, everyday. How long will each p...

    Text Solution

    |

  8. If 7 spiders make 7 webs in 7 days, then 1 spider will make 1 web in h...

    Text Solution

    |

  9. Sister can bake 50 cakes in 25 hours, Sister and Mummy together can ba...

    Text Solution

    |

  10. A can do a work in 15 days and B in 20 days.If they together work on i...

    Text Solution

    |

  11. A can complete a piece of work in 18 days and B can complete the same ...

    Text Solution

    |

  12. A does (7)/(10) part of work in 15 days. After that he completes the r...

    Text Solution

    |

  13. A can do (1)/(2) of a piece of work in 5 days B can do (3)/(5) of the ...

    Text Solution

    |

  14. If 28 men complete (7)/(8) of a plece of work in a week, then the numb...

    Text Solution

    |

  15. P can complete (1)/(3) of a work in 10 days, Q can complete 40% of the...

    Text Solution

    |

  16. A alone can do a plece of work in 20 days and B alone in 30 days. They...

    Text Solution

    |

  17. A does half as much work as B in three fourth of the times. If togethe...

    Text Solution

    |

  18. A can do one and a half as much of a work which B can do in one day. B...

    Text Solution

    |

  19. Two workers A and B are engaged to do a piece of work. A working alone...

    Text Solution

    |

  20. A company employed 200 workers to complete a certain work in 150 days....

    Text Solution

    |