B would have taken 10 hours more than wh...

B would have taken 10 hours more than what A would have taken to complete a task if each of them worked alone. Working together they can complete the task in 12 hours. How many hours would B take to do 50% of the task?

A

30

B

15

C

20

D

10

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

The efficiencies of A, B, and C are in the ratio 2 : 5 : 3. Working together, they can complete a task in 12 days. In how many days can A alone complete 30% of that task ?

A takes 5 hours more time than that taken by B to complete a work. If working together they can complete a work in 6 hours, then the number of hours that takes to complete the work individually is

3 boys and 3 girls can complete a task in (6)/(5) hours. How many hours will 1 boy and 1 girl require to complete the task?

KIRAN PUBLICATION-TIME AND WORK-TYPE-VI
  1. A can do in one day three times the work done by B in one day. They to...

    Text Solution

    |

  2. Janardan completes (2)/(3) of his work in 10 days. Time he will take t...

    Text Solution

    |

  3. John does (1)/(2) piece of work in 3 hours, Joe does (1)/(4) of the re...

    Text Solution

    |

  4. A and B work together to complete the rest of a job in 7 days. However...

    Text Solution

    |

  5. Dhiru can dig (1)/(a) of a field in 20 hours. What fraction of the sam...

    Text Solution

    |

  6. A can do a certain job in 12 days. B is 60% more efficient than A. The...

    Text Solution

    |

  7. A, B and C contract a work for Rs. 440. A and B together are to do (9)...

    Text Solution

    |

  8. A painter can paint a fence in 24 hours. After 6 hours he takes a brea...

    Text Solution

    |

  9. Akka can bake 100 cakes in 20 hours, Akka and Tai together can bake 75...

    Text Solution

    |

  10. B would have taken 10 hours more than what A would have taken to compl...

    Text Solution

    |

  11. A can do 50% of the job in 16 days, B can do (1)/(4)th of the job in 2...

    Text Solution

    |

  12. A can do a work in 21 days and B in 42 days. If they work on it toget...

    Text Solution

    |

  13. A, B and C can together do a job in 9 days. C alone can do the job in ...

    Text Solution

    |

  14. A can do a work in 72 days and B in 90 days. If they work on it togeth...

    Text Solution

    |

  15. M can complete (3)/(4) part of a work in 12 days and N can complete (2...

    Text Solution

    |

  16. A does half as much work as B in three fourth of the times. If togethe...

    Text Solution

    |

  17. S does half as much work as T in (1)/(7) of the time taken by T. If to...

    Text Solution

    |

  18. X can complete (5)/(7) th part of a work in 10 days and Y can complete...

    Text Solution

    |

  19. X and Y can complete a work in 5 days. Y and Z can complete the same w...

    Text Solution

    |

  20. X can complete a work in 27 days and Y can do the same work in half of...

    Text Solution

    |