X can complete a work in 27 days and Y can do the same work in half of the time taken by X Working together what part of the same work can they complete in a day?

A

A)`(1)/(9)`

B

B)`(1)/(6)`

C

C)`(1)/(12)`

D

D)`(2)/(27)`

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos
  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-V|19 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?

A can finish a work in 15 days and B can do the same work in twice the time taken by A. then, working together, what part of the same work they can finish in five days?

A can finish a work in 15 days and B can do the same work in twice the time taken by A. then, working together. What part of the same work they can finish in five days ?

A can complete a work in 18 hours and B can complete the same work in half of his time.If they start working together then how much part will the complete in one day?

A can complete a work in 18 days, B can do the same work in half the time as A. What part of work can be completed by both of them working together in 1 day

A can complete a work in 12 days and B complete the same work in 15 days. Find the time taken by them when A and B worked together.

A can complete a work in 20 days and B can complete the same work in 25 days . If both of them work together, in 3 days what per cant of the total work will be completed ?

KIRAN PUBLICATION-TIME AND WORK-TYPE-VI
  1. A can do in one day three times the work done by B in one day. They to...

    Text Solution

    |

  2. Janardan completes (2)/(3) of his work in 10 days. Time he will take t...

    Text Solution

    |

  3. John does (1)/(2) piece of work in 3 hours, Joe does (1)/(4) of the re...

    Text Solution

    |

  4. A and B work together to complete the rest of a job in 7 days. However...

    Text Solution

    |

  5. Dhiru can dig (1)/(a) of a field in 20 hours. What fraction of the sam...

    Text Solution

    |

  6. A can do a certain job in 12 days. B is 60% more efficient than A. The...

    Text Solution

    |

  7. A, B and C contract a work for Rs. 440. A and B together are to do (9)...

    Text Solution

    |

  8. A painter can paint a fence in 24 hours. After 6 hours he takes a brea...

    Text Solution

    |

  9. Akka can bake 100 cakes in 20 hours, Akka and Tai together can bake 75...

    Text Solution

    |

  10. B would have taken 10 hours more than what A would have taken to compl...

    Text Solution

    |

  11. A can do 50% of the job in 16 days, B can do (1)/(4)th of the job in 2...

    Text Solution

    |

  12. A can do a work in 21 days and B in 42 days. If they work on it toget...

    Text Solution

    |

  13. A, B and C can together do a job in 9 days. C alone can do the job in ...

    Text Solution

    |

  14. A can do a work in 72 days and B in 90 days. If they work on it togeth...

    Text Solution

    |

  15. M can complete (3)/(4) part of a work in 12 days and N can complete (2...

    Text Solution

    |

  16. A does half as much work as B in three fourth of the times. If togethe...

    Text Solution

    |

  17. S does half as much work as T in (1)/(7) of the time taken by T. If to...

    Text Solution

    |

  18. X can complete (5)/(7) th part of a work in 10 days and Y can complete...

    Text Solution

    |

  19. X and Y can complete a work in 5 days. Y and Z can complete the same w...

    Text Solution

    |

  20. X can complete a work in 27 days and Y can do the same work in half of...

    Text Solution

    |