Home
Class 14
MATHS
A, B and C can complete a work In 8 days...

A, B and C can complete a work In 8 days. B alone can do it in 18 days and Calone can do it in 24 days. In how many days can A alone do the same work?

A

36 days

B

24 days

C

38 days

D

30 days

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-VI|59 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A and B can do a work in 8 days and A alone can do it in 12 days. In how many days can B alone do it?

A and B together can do a work in 30 days and A alone can do it in 40 days. In how many days B alone can do this?

A alone can do a piece of work in 10 days and B alone can do it in 15 days. In how many days will A and B together do the same work?

A and B can do a piece of work in 8 days. B and C can do it in 24 days, while C and A can do it in 8 4/7 days. In how many days can C do it alone?

A and B can do a piece of work in S days. B and C can do it in 24 days while C and A can do it in 8(4/7) days. In how many days can C do it alone?

A and B together can do a piece of work in 12 days and A alone can do it in 18 days. In how many days canBalone do it?

KIRAN PUBLICATION-TIME AND WORK-TEST YOURSELF
  1. A can do a work in 12 days and B can do it in 16 days. A and B started...

    Text Solution

    |

  2. Ram can do a piece of work in 20 days and Shyam in 30 days. They work ...

    Text Solution

    |

  3. A and B can complete a piece of work in 45 and 40 days respectively. B...

    Text Solution

    |

  4. A can do a piece of work in 40 days. He works on it for 5 days and the...

    Text Solution

    |

  5. Rita, Sita and Meeta are employed to do a piece of work for Rs 625. Ri...

    Text Solution

    |

  6. A and B can do a piece of work in 10 days, B and C in 15 days and C an...

    Text Solution

    |

  7. A, B and C can complete a work In 8 days. B alone can do it in 18 days...

    Text Solution

    |

  8. A alone takes as much time as B and C together take to complete a piec...

    Text Solution

    |

  9. A and B together can finish a work in 15 days. A and C take 2 days mor...

    Text Solution

    |

  10. A and B together can do a piece of work in 30 days, B and C together c...

    Text Solution

    |

  11. A and B can do a piece of work in 12 days, B and C in 15 days, C and A...

    Text Solution

    |

  12. A can complete a work in 24 days, B in 32 days and C in 64 days. They ...

    Text Solution

    |

  13. A, B and C can complete a work separately in 24, 36 and 48 days respec...

    Text Solution

    |

  14. A can complete a work in 10 days, B can complete the same work in 20 d...

    Text Solution

    |

  15. A can do a piece of work in 120 days and B can do it in 150 days. They...

    Text Solution

    |

  16. A and B can do a piece of work in 30 days while B and C can do the sam...

    Text Solution

    |

  17. 9 children can complete a plece of work in 360 days. 18 men can comple...

    Text Solution

    |

  18. The work done by a woman in 8 hours is equal to the work done by a man...

    Text Solution

    |

  19. 12 men can complete a piece of work in 4 days, while 15 women can comp...

    Text Solution

    |

  20. 8 men and 4 women together can complete a piece of work in 6 days. Wor...

    Text Solution

    |