Home
Class 14
MATHS
A can complete a work in 24 days, B in 3...

A can complete a work in 24 days, B in 32 days and C in 64 days. They start together. A works for 6 days and leaves and B leaves 6 days before the work is finished. In how many days was the work finished?

A

20 days

B

21 days

C

22 days

D

25 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will calculate the work done by A, B, and C, and determine how long it takes to finish the work under the given conditions. ### Step 1: Determine the work rates of A, B, and C - A can complete the work in 24 days, so A's work rate is \( \frac{1}{24} \) of the work per day. - B can complete the work in 32 days, so B's work rate is \( \frac{1}{32} \) of the work per day. - C can complete the work in 64 days, so C's work rate is \( \frac{1}{64} \) of the work per day. ### Step 2: Calculate the combined work rate of A, B, and C To find the combined work rate, we sum their individual rates: \[ \text{Combined work rate} = \frac{1}{24} + \frac{1}{32} + \frac{1}{64} \] To add these fractions, we need a common denominator. The least common multiple (LCM) of 24, 32, and 64 is 192. We convert each fraction: - \( \frac{1}{24} = \frac{8}{192} \) - \( \frac{1}{32} = \frac{6}{192} \) - \( \frac{1}{64} = \frac{3}{192} \) Now, adding them together: \[ \text{Combined work rate} = \frac{8 + 6 + 3}{192} = \frac{17}{192} \] So, together they can complete \( \frac{17}{192} \) of the work in one day. ### Step 3: Calculate the work done in the first 6 days A works for 6 days, so the work done by A, B, and C in those 6 days is: \[ \text{Work done in 6 days} = 6 \times \frac{17}{192} = \frac{102}{192} \] This simplifies to: \[ \frac{102}{192} = \frac{51}{96} \] ### Step 4: Calculate the remaining work The total work is considered as 1 (or 192 units). The remaining work after 6 days is: \[ \text{Remaining work} = 1 - \frac{51}{96} = \frac{96 - 51}{96} = \frac{45}{96} = \frac{15}{32} \] ### Step 5: Determine who works after A leaves After 6 days, A leaves, and B leaves 6 days before the work is finished. This means C will work alone for the last 6 days. ### Step 6: Calculate the work done by C in the last 6 days C's work rate is \( \frac{1}{64} \) of the work per day. Therefore, in 6 days, C will do: \[ \text{Work done by C in 6 days} = 6 \times \frac{1}{64} = \frac{6}{64} = \frac{3}{32} \] ### Step 7: Calculate the remaining work after C's contribution The remaining work after C works for 6 days is: \[ \text{Remaining work} = \frac{15}{32} - \frac{3}{32} = \frac{12}{32} = \frac{3}{8} \] ### Step 8: Determine how long B and C will work together to finish the remaining work B and C will work together to complete the remaining \( \frac{3}{8} \) of the work. Their combined work rate is: \[ \text{B's work rate} + \text{C's work rate} = \frac{1}{32} + \frac{1}{64} \] Finding a common denominator (64): \[ \frac{1}{32} = \frac{2}{64} \] Thus, \[ \text{Combined work rate of B and C} = \frac{2}{64} + \frac{1}{64} = \frac{3}{64} \] ### Step 9: Calculate the time taken by B and C to finish the remaining work To find the time \( t \) taken to finish \( \frac{3}{8} \) of the work: \[ \frac{3}{8} = t \times \frac{3}{64} \] Solving for \( t \): \[ t = \frac{3/8}{3/64} = \frac{3}{8} \times \frac{64}{3} = 8 \text{ days} \] ### Step 10: Calculate the total time taken to finish the work The total time taken to complete the work is: \[ \text{Total time} = 6 \text{ (days A worked)} + 8 \text{ (days B and C worked)} = 14 \text{ days} \] ### Final Answer The work was finished in **14 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-VI|59 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 10 days,B in 12 days and C in 15 days.All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished.How long did the work last?

Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?

A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

A can complete a work in 16 days, B in 12 days and C in l5 days. All of them began the work together, but A had to leave the work after 2 days of the start and B 3 days before the completion of the work. How long did the work last?

KIRAN PUBLICATION-TIME AND WORK-TEST YOURSELF
  1. A can do a work in 12 days and B can do it in 16 days. A and B started...

    Text Solution

    |

  2. Ram can do a piece of work in 20 days and Shyam in 30 days. They work ...

    Text Solution

    |

  3. A and B can complete a piece of work in 45 and 40 days respectively. B...

    Text Solution

    |

  4. A can do a piece of work in 40 days. He works on it for 5 days and the...

    Text Solution

    |

  5. Rita, Sita and Meeta are employed to do a piece of work for Rs 625. Ri...

    Text Solution

    |

  6. A and B can do a piece of work in 10 days, B and C in 15 days and C an...

    Text Solution

    |

  7. A, B and C can complete a work In 8 days. B alone can do it in 18 days...

    Text Solution

    |

  8. A alone takes as much time as B and C together take to complete a piec...

    Text Solution

    |

  9. A and B together can finish a work in 15 days. A and C take 2 days mor...

    Text Solution

    |

  10. A and B together can do a piece of work in 30 days, B and C together c...

    Text Solution

    |

  11. A and B can do a piece of work in 12 days, B and C in 15 days, C and A...

    Text Solution

    |

  12. A can complete a work in 24 days, B in 32 days and C in 64 days. They ...

    Text Solution

    |

  13. A, B and C can complete a work separately in 24, 36 and 48 days respec...

    Text Solution

    |

  14. A can complete a work in 10 days, B can complete the same work in 20 d...

    Text Solution

    |

  15. A can do a piece of work in 120 days and B can do it in 150 days. They...

    Text Solution

    |

  16. A and B can do a piece of work in 30 days while B and C can do the sam...

    Text Solution

    |

  17. 9 children can complete a plece of work in 360 days. 18 men can comple...

    Text Solution

    |

  18. The work done by a woman in 8 hours is equal to the work done by a man...

    Text Solution

    |

  19. 12 men can complete a piece of work in 4 days, while 15 women can comp...

    Text Solution

    |

  20. 8 men and 4 women together can complete a piece of work in 6 days. Wor...

    Text Solution

    |