Home
Class 14
MATHS
12 men can complete a piece of work in 4...

12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job and after working for two days, all of them stopped working. How many women should be put on the job to complete the remaining work, if It is to be completed in 3 days

A

15

B

22

C

18

D

Data inadequate

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Calculate the total work done by men and women We know that: - 12 men can complete the work in 4 days. - 15 women can also complete the same work in 4 days. First, we calculate the total work in terms of man-days and woman-days. Total work done by men: \[ \text{Total Work} = \text{Number of Men} \times \text{Days} = 12 \text{ men} \times 4 \text{ days} = 48 \text{ man-days} \] Total work done by women: \[ \text{Total Work} = \text{Number of Women} \times \text{Days} = 15 \text{ women} \times 4 \text{ days} = 60 \text{ woman-days} \] ### Step 2: Equate the total work done by men and women Since both complete the same work: \[ 48 \text{ man-days} = 60 \text{ woman-days} \] From this, we can find the efficiency ratio of men to women: \[ \frac{M}{W} = \frac{60}{48} = \frac{5}{4} \] This means that 5 man-days are equivalent to 4 woman-days. ### Step 3: Calculate the work done by 6 men in 2 days Now, we need to find out how much work 6 men can do in 2 days. The efficiency of 1 man is: \[ \text{Efficiency of 1 man} = \frac{48 \text{ man-days}}{12 \text{ men} \times 4 \text{ days}} = 1 \text{ unit of work per day} \] Thus, the work done by 6 men in 1 day: \[ \text{Work done by 6 men in 1 day} = 6 \text{ men} \times 1 \text{ unit} = 6 \text{ units} \] In 2 days, the work done will be: \[ \text{Total work done by 6 men in 2 days} = 6 \text{ units/day} \times 2 \text{ days} = 12 \text{ units} \] ### Step 4: Calculate the remaining work The total work is 48 units (from Step 1). The remaining work after 6 men have worked for 2 days is: \[ \text{Remaining Work} = 48 \text{ units} - 12 \text{ units} = 36 \text{ units} \] ### Step 5: Determine how many women are needed to complete the remaining work in 3 days Let \( x \) be the number of women needed to complete the remaining 36 units of work in 3 days. The work done by \( x \) women in 3 days is: \[ \text{Work done by } x \text{ women in 3 days} = x \text{ women} \times 3 \text{ days} \times \frac{4 \text{ units}}{1 \text{ woman}} = 12x \text{ units} \] Setting this equal to the remaining work: \[ 12x = 36 \] ### Step 6: Solve for \( x \) Dividing both sides by 12: \[ x = \frac{36}{12} = 3 \] ### Conclusion Thus, **3 women** are needed to complete the remaining work in 3 days. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    KIRAN PUBLICATION|Exercise TYPE-VI|59 Videos
  • TIME AND DISTANCE

    KIRAN PUBLICATION|Exercise Type -XI|74 Videos
  • TRIGONOMETRY

    KIRAN PUBLICATION|Exercise TEST YOURSELF|25 Videos

Similar Questions

Explore conceptually related problems

12 men can complete a piece of work in 4 days,while 15 women can complete the same work in 4 days.6 men start working on the job and after working for 2 days,all of them stopped working.How many women should be put on the job to complete the remaining work,if it is to be completed in 3days?

15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?

10 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, in how many days will the work get completed?

12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?

21 men can complete a piece of work in 42/7 days. In how many days can 18 men complete the same piece of work?

Twenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?

Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working and worked for twelve days.How many more men are to be added to complete the remaining work in 2 days?

KIRAN PUBLICATION-TIME AND WORK-TEST YOURSELF
  1. A can do a work in 12 days and B can do it in 16 days. A and B started...

    Text Solution

    |

  2. Ram can do a piece of work in 20 days and Shyam in 30 days. They work ...

    Text Solution

    |

  3. A and B can complete a piece of work in 45 and 40 days respectively. B...

    Text Solution

    |

  4. A can do a piece of work in 40 days. He works on it for 5 days and the...

    Text Solution

    |

  5. Rita, Sita and Meeta are employed to do a piece of work for Rs 625. Ri...

    Text Solution

    |

  6. A and B can do a piece of work in 10 days, B and C in 15 days and C an...

    Text Solution

    |

  7. A, B and C can complete a work In 8 days. B alone can do it in 18 days...

    Text Solution

    |

  8. A alone takes as much time as B and C together take to complete a piec...

    Text Solution

    |

  9. A and B together can finish a work in 15 days. A and C take 2 days mor...

    Text Solution

    |

  10. A and B together can do a piece of work in 30 days, B and C together c...

    Text Solution

    |

  11. A and B can do a piece of work in 12 days, B and C in 15 days, C and A...

    Text Solution

    |

  12. A can complete a work in 24 days, B in 32 days and C in 64 days. They ...

    Text Solution

    |

  13. A, B and C can complete a work separately in 24, 36 and 48 days respec...

    Text Solution

    |

  14. A can complete a work in 10 days, B can complete the same work in 20 d...

    Text Solution

    |

  15. A can do a piece of work in 120 days and B can do it in 150 days. They...

    Text Solution

    |

  16. A and B can do a piece of work in 30 days while B and C can do the sam...

    Text Solution

    |

  17. 9 children can complete a plece of work in 360 days. 18 men can comple...

    Text Solution

    |

  18. The work done by a woman in 8 hours is equal to the work done by a man...

    Text Solution

    |

  19. 12 men can complete a piece of work in 4 days, while 15 women can comp...

    Text Solution

    |

  20. 8 men and 4 women together can complete a piece of work in 6 days. Wor...

    Text Solution

    |