Home
Class 8
MATHS
24 men can complete a piece of work in 1...

24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work done by men and women, then calculate how much work is left after 16 days, and finally find out how many additional men are needed to complete the remaining work in 2 days. ### Step 1: Calculate the work done by men and women 1. **Work done by 24 men in 16 days:** - Total work = Number of men × Number of days = 24 men × 16 days = 384 man-days. - Therefore, 1 man can complete \( \frac{1}{384} \) of the work in one day. 2. **Work done by 18 women in 32 days:** - Total work = Number of women × Number of days = 18 women × 32 days = 576 woman-days. - Therefore, 1 woman can complete \( \frac{1}{576} \) of the work in one day. ### Step 2: Calculate the work done by 12 men and 6 women in 16 days 1. **Work done by 12 men in 1 day:** - Work done by 12 men in 1 day = \( 12 \times \frac{1}{384} = \frac{12}{384} = \frac{1}{32} \). 2. **Work done by 6 women in 1 day:** - Work done by 6 women in 1 day = \( 6 \times \frac{1}{576} = \frac{6}{576} = \frac{1}{96} \). 3. **Total work done by 12 men and 6 women in 1 day:** - Total work in 1 day = Work done by men + Work done by women = \( \frac{1}{32} + \frac{1}{96} \). - To add these fractions, we find a common denominator, which is 96: - \( \frac{1}{32} = \frac{3}{96} \). - Therefore, \( \frac{1}{32} + \frac{1}{96} = \frac{3}{96} + \frac{1}{96} = \frac{4}{96} = \frac{1}{24} \). 4. **Work done in 16 days:** - Work done in 16 days = \( 16 \times \frac{1}{24} = \frac{16}{24} = \frac{2}{3} \). ### Step 3: Calculate the remaining work 1. **Remaining work:** - Total work = 1 (whole work). - Work done = \( \frac{2}{3} \). - Remaining work = \( 1 - \frac{2}{3} = \frac{1}{3} \). ### Step 4: Calculate how many additional men are required to complete the remaining work in 2 days 1. **Work done by 12 men and 6 women in 2 days:** - Work done by 12 men in 2 days = \( 2 \times \frac{1}{32} = \frac{2}{32} = \frac{1}{16} \). - Work done by 6 women in 2 days = \( 2 \times \frac{1}{96} = \frac{2}{96} = \frac{1}{48} \). - Total work done in 2 days = \( \frac{1}{16} + \frac{1}{48} \). - To add these fractions, we find a common denominator, which is 48: - \( \frac{1}{16} = \frac{3}{48} \). - Therefore, \( \frac{1}{16} + \frac{1}{48} = \frac{3}{48} + \frac{1}{48} = \frac{4}{48} = \frac{1}{12} \). 2. **Remaining work after 2 days:** - Remaining work = \( \frac{1}{3} - \frac{1}{12} \). - To subtract these fractions, we find a common denominator, which is 12: - \( \frac{1}{3} = \frac{4}{12} \). - Therefore, \( \frac{1}{3} - \frac{1}{12} = \frac{4}{12} - \frac{1}{12} = \frac{3}{12} = \frac{1}{4} \). ### Step 5: Calculate how many additional men are required to complete the remaining work in 2 days 1. **Let n be the number of additional men required.** - Work done by \( 12 + n \) men in 2 days = \( (12 + n) \times \frac{1}{384} \times 2 \). - This should equal the remaining work \( \frac{1}{4} \): \[ (12 + n) \times \frac{2}{384} = \frac{1}{4} \] - Simplifying gives: \[ (12 + n) \times \frac{1}{192} = \frac{1}{4} \] - Cross-multiplying: \[ 12 + n = 48 \] - Therefore, \( n = 48 - 12 = 36 \). ### Final Answer **36 additional men are required.**
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Question Bank - 20 (a)|27 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Question Bank - 20 (b)|15 Videos
  • SURDS

    S CHAND IIT JEE FOUNDATION|Exercise UNIT TEST -1 |15 Videos
  • TRIANGLES

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet|10 Videos

Similar Questions

Explore conceptually related problems

15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

10 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, in how many days will the work get completed?

12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?

3 men can do a piece of work in 6 days. 5 women can do the same work in 18 days. If 4 men and 10 women work together, then how long will it take to finish the work?

12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?

21 men can complete a piece of work in 42/7 days. In how many days can 18 men complete the same piece of work?

6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required? 36 b. 24 c. 18 d. cannot be determined