A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

A

10 days

B

20 days

C

15 days

D

6 days

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Question Bank - 20 (b)|15 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 20|10 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 20|10 Videos
  • SURDS

    S CHAND IIT JEE FOUNDATION|Exercise UNIT TEST -1 |15 Videos
  • TRIANGLES

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet|10 Videos

Similar Questions

Explore conceptually related problems

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last? 6 d a y s b. 10 d a y s c. 1 5 d a y s d. 20 d a y s

X and Y can do a piece of work in 20 days and 12 days respectively. X started line work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?

A and B can do a piece of work in 6 and 12 days, respectively. They (both) will complete the work in how many days?

A and B can do a piece of work in 20 days and 30 days respectively. A start the work and they do this work in alternate days. In how many days will this work be completed ?

A\ a n d\ B can do a piece of work in 6 days and 4 days respectively. A started the work; worked at it for 2 days and then was joined by B . Find the total time taken to complete the work.

A and B can do a piece of work in 20 days and 25 days. A start the work and they do this work in alternate days. In how many days will this work be completed ?

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

B is twice efficient as A and A can do a piece of work in 15 days. A started the work and after a few days B joined him. They completed the work in 11 days, from the starting. For how many days they worked together?

S CHAND IIT JEE FOUNDATION-TIME AND WORK -Question Bank - 20 (a)
  1. 40 men can do a piece of work in a given time. If only 30 men be engag...

    Text Solution

    |

  2. A man and a boy working together can complete a work in 24 days. If fo...

    Text Solution

    |

  3. A and B can do a piece of work in 20 days and 12 days respectively. A ...

    Text Solution

    |

  4. A and B can do a piece of work in 28 and 35 days respectively. They be...

    Text Solution

    |

  5. A alone can do a piece of work in 6 days and B alone in 8 days. A and ...

    Text Solution

    |

  6. If 20 men working 7 hours a day can do a piece of work in 10 days, in ...

    Text Solution

    |

  7. 12 cows together eat 756 kg of grass in 7 days. How much grass will be...

    Text Solution

    |

  8. If 5 spiders can catch 5 flies in 5 minutes, how many flies can 100 sp...

    Text Solution

    |

  9. 8 men working for 9 hours a day can complete a piece of work in 20 day...

    Text Solution

    |

  10. A job can be completed by 12 men in 12 days. How many extra days will ...

    Text Solution

    |

  11. A contractor undertakes to complete a road 360 m long in 120 days and ...

    Text Solution

    |

  12. A wall of 100 metres can be built by 7 men or 10 women in 10 days. How...

    Text Solution

    |

  13. Twenty four men can complete a work in sixteen days. Thirty two women ...

    Text Solution

    |

  14. 12 men and 16 boys can do a piece of work in 5 days, 13 men and 24 boy...

    Text Solution

    |

  15. Three men four women and six children can complete a work in seven ...

    Text Solution

    |

  16. A man a wma and a boy can complete a job in 3,4, and 12 days respec...

    Text Solution

    |

  17. A machine P can print one lakh books in 8 hours, machine Q can prin...

    Text Solution

    |

  18. A takes 5 hours more time than that taken by B to complete a work. If ...

    Text Solution

    |

  19. If x men, working x hours per day, can do x units of work in x days, t...

    Text Solution

    |

  20. A started a work and left after working for 2 days. Then B was call...

    Text Solution

    |