A wall of 100 metres can be built by 7 men or 10 women in 10 days. How many days will 14 men and 20 women take to build a wall of 600 metres ?

A

15

B

20

C

25

D

30

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work done by men and women in terms of a common unit, then calculate how long it will take for 14 men and 20 women to build a wall of 600 meters. ### Step 1: Determine the work done by men and women Given that: - 7 men can build a wall of 100 meters in 10 days. - 10 women can also build a wall of 100 meters in 10 days. From this, we can find the work done by one man and one woman. ### Step 2: Calculate the work done by one man in one day The total work done (in terms of wall area) can be calculated as: - Work done by 7 men in 10 days = 100 meters - Therefore, work done by 1 man in 10 days = 100 meters / 7 = approximately 14.29 meters. Now, work done by 1 man in 1 day: \[ \text{Work done by 1 man in 1 day} = \frac{14.29 \text{ meters}}{10 \text{ days}} = 1.429 \text{ meters/day} \] ### Step 3: Calculate the work done by one woman in one day Similarly, for women: - Work done by 10 women in 10 days = 100 meters - Therefore, work done by 1 woman in 10 days = 100 meters / 10 = 10 meters. Now, work done by 1 woman in 1 day: \[ \text{Work done by 1 woman in 1 day} = \frac{10 \text{ meters}}{10 \text{ days}} = 1 \text{ meter/day} \] ### Step 4: Convert the workforce of 14 men and 20 women into equivalent work done per day Now, we can calculate the total work done by 14 men and 20 women in one day: - Work done by 14 men in one day: \[ \text{Work done by 14 men} = 14 \times 1.429 \text{ meters/day} = 20.006 \text{ meters/day} \] - Work done by 20 women in one day: \[ \text{Work done by 20 women} = 20 \times 1 \text{ meter/day} = 20 \text{ meters/day} \] ### Step 5: Total work done by 14 men and 20 women in one day Now, adding both contributions: \[ \text{Total work done in one day} = 20.006 + 20 = 40.006 \text{ meters/day} \] ### Step 6: Calculate the time required to build 600 meters To find out how many days it will take to build a wall of 600 meters: \[ \text{Days required} = \frac{600 \text{ meters}}{40.006 \text{ meters/day}} \approx 14.99 \text{ days} \] Since we cannot have a fraction of a day in practical terms, we round it up to 15 days. ### Final Answer: It will take approximately **15 days** for 14 men and 20 women to build a wall of 600 meters. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Question Bank - 20 (b)|15 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 20|10 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 20|10 Videos
  • SURDS

    S CHAND IIT JEE FOUNDATION|Exercise UNIT TEST -1 |15 Videos
  • TRIANGLES

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet|10 Videos

Similar Questions

Explore conceptually related problems

A field can be reaped by 12 men or 18 women in 14 days. In how many days can 8 men and 16 women reap it?

6 men or 8 women can do a job in 10 days In how many days can 5 men and 9 women do the same job?

5 men working 8 hours a day can completely build a wall of length 20 metres, breadth 1/4 metre and height 6 metres in 3 days. How many days will 8 men working 6 hours a day require to build a wall of length 120 meters, breadth 1/2 metre and height 4 metres.

If 3 men or 4 women can reap a field in 43 days. How long will 7 men and 5 women take to reap it?

If 12 men or 18 women can do a work in 14 days,then in how many days will 8 men and 16 women do the same work?

If 3 men or 4 women can reap a field in 43 days, how long will 7 men and 5 women take to reap it?

S CHAND IIT JEE FOUNDATION-TIME AND WORK -Question Bank - 20 (a)
  1. A man and a boy working together can complete a work in 24 days. If fo...

    Text Solution

    |

  2. A and B can do a piece of work in 20 days and 12 days respectively. A ...

    Text Solution

    |

  3. A and B can do a piece of work in 28 and 35 days respectively. They be...

    Text Solution

    |

  4. A alone can do a piece of work in 6 days and B alone in 8 days. A and ...

    Text Solution

    |

  5. If 20 men working 7 hours a day can do a piece of work in 10 days, in ...

    Text Solution

    |

  6. 12 cows together eat 756 kg of grass in 7 days. How much grass will be...

    Text Solution

    |

  7. If 5 spiders can catch 5 flies in 5 minutes, how many flies can 100 sp...

    Text Solution

    |

  8. 8 men working for 9 hours a day can complete a piece of work in 20 day...

    Text Solution

    |

  9. A job can be completed by 12 men in 12 days. How many extra days will ...

    Text Solution

    |

  10. A contractor undertakes to complete a road 360 m long in 120 days and ...

    Text Solution

    |

  11. A wall of 100 metres can be built by 7 men or 10 women in 10 days. How...

    Text Solution

    |

  12. Twenty four men can complete a work in sixteen days. Thirty two women ...

    Text Solution

    |

  13. 12 men and 16 boys can do a piece of work in 5 days, 13 men and 24 boy...

    Text Solution

    |

  14. Three men four women and six children can complete a work in seven ...

    Text Solution

    |

  15. A man a wma and a boy can complete a job in 3,4, and 12 days respec...

    Text Solution

    |

  16. A machine P can print one lakh books in 8 hours, machine Q can prin...

    Text Solution

    |

  17. A takes 5 hours more time than that taken by B to complete a work. If ...

    Text Solution

    |

  18. If x men, working x hours per day, can do x units of work in x days, t...

    Text Solution

    |

  19. A started a work and left after working for 2 days. Then B was call...

    Text Solution

    |

  20. 15 men can complete a work in 210 days. They started the work but at t...

    Text Solution

    |