Twenty four men can complete a work in s...

Twenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?

A

16

B

24

C

36

D

48

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Question Bank - 20 (b)|15 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 20|10 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 20|10 Videos
  • SURDS

    S CHAND IIT JEE FOUNDATION|Exercise UNIT TEST -1 |15 Videos
  • TRIANGLES

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet|10 Videos

Similar Questions

Explore conceptually related problems

Twenty-four men can complete a work in sixteen days.Thirty-two women can complete the same work in twenty-four days.Sixteen men and sixteen women started working and worked for twelve days.How many more men are to be added to complete the remaining work in 2 days?

If 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?

20 men can do a work in 35 days. How many men are needed to complete the same work in 25 days.

12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?

15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

7 men can complete a work in 52 days. In how many days will 13 men finish the same work.

S CHAND IIT JEE FOUNDATION-TIME AND WORK -Question Bank - 20 (a)
  1. A man and a boy working together can complete a work in 24 days. If fo...

    Text Solution

    |

  2. A and B can do a piece of work in 20 days and 12 days respectively. A ...

    Text Solution

    |

  3. A and B can do a piece of work in 28 and 35 days respectively. They be...

    Text Solution

    |

  4. A alone can do a piece of work in 6 days and B alone in 8 days. A and ...

    Text Solution

    |

  5. If 20 men working 7 hours a day can do a piece of work in 10 days, in ...

    Text Solution

    |

  6. 12 cows together eat 756 kg of grass in 7 days. How much grass will be...

    Text Solution

    |

  7. If 5 spiders can catch 5 flies in 5 minutes, how many flies can 100 sp...

    Text Solution

    |

  8. 8 men working for 9 hours a day can complete a piece of work in 20 day...

    Text Solution

    |

  9. A job can be completed by 12 men in 12 days. How many extra days will ...

    Text Solution

    |

  10. A contractor undertakes to complete a road 360 m long in 120 days and ...

    Text Solution

    |

  11. A wall of 100 metres can be built by 7 men or 10 women in 10 days. How...

    Text Solution

    |

  12. Twenty four men can complete a work in sixteen days. Thirty two women ...

    Text Solution

    |

  13. 12 men and 16 boys can do a piece of work in 5 days, 13 men and 24 boy...

    Text Solution

    |

  14. Three men four women and six children can complete a work in seven ...

    Text Solution

    |

  15. A man a wma and a boy can complete a job in 3,4, and 12 days respec...

    Text Solution

    |

  16. A machine P can print one lakh books in 8 hours, machine Q can prin...

    Text Solution

    |

  17. A takes 5 hours more time than that taken by B to complete a work. If ...

    Text Solution

    |

  18. If x men, working x hours per day, can do x units of work in x days, t...

    Text Solution

    |

  19. A started a work and left after working for 2 days. Then B was call...

    Text Solution

    |

  20. 15 men can complete a work in 210 days. They started the work but at t...

    Text Solution

    |