Home
Class 8
MATHS
It takes 8,12 and 16 days for X, Y and Z...

It takes 8,12 and 16 days for X, Y and Z respectively to complete a work. How many days will it take to complete the work if X works on it for 2 days, and then Y works on it for until 25% of the work is left for Z to do, and then Z complete the work?

A

10 days

B

12 days

C

8 days

D

14 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step-by-step, we will break it down into manageable parts. ### Step 1: Determine the work done by X, Y, and Z in one day. - X completes the work in 8 days, so the work done by X in one day is: \[ \text{Work done by X in 1 day} = \frac{1}{8} \] - Y completes the work in 12 days, so the work done by Y in one day is: \[ \text{Work done by Y in 1 day} = \frac{1}{12} \] - Z completes the work in 16 days, so the work done by Z in one day is: \[ \text{Work done by Z in 1 day} = \frac{1}{16} \] ### Step 2: Calculate the work done by X in 2 days. - In 2 days, X will complete: \[ \text{Work done by X in 2 days} = 2 \times \frac{1}{8} = \frac{2}{8} = \frac{1}{4} \] ### Step 3: Calculate the remaining work after X works for 2 days. - The total work is considered as 1 (or 100%). After X completes \(\frac{1}{4}\) of the work, the remaining work is: \[ \text{Remaining work} = 1 - \frac{1}{4} = \frac{3}{4} \] ### Step 4: Determine how much work Y needs to do before leaving 25% of the work for Z. - 25% of the total work is: \[ 25\% = \frac{25}{100} = \frac{1}{4} \] - Therefore, Y will work until \(\frac{1}{4}\) of the work is left, which means Y will complete: \[ \text{Work done by Y} = \frac{3}{4} - \frac{1}{4} = \frac{2}{4} = \frac{1}{2} \] ### Step 5: Calculate how many days Y takes to complete \(\frac{1}{2}\) of the work. - Since Y does \(\frac{1}{12}\) of the work in one day, the number of days Y needs to complete \(\frac{1}{2}\) of the work is: \[ \text{Days taken by Y} = \frac{\frac{1}{2}}{\frac{1}{12}} = \frac{1}{2} \times \frac{12}{1} = 6 \text{ days} \] ### Step 6: Calculate the work remaining for Z. - After Y completes \(\frac{1}{2}\) of the work, the remaining work for Z is: \[ \text{Remaining work for Z} = \frac{1}{4} \text{ (as calculated earlier)} \] ### Step 7: Calculate how many days Z takes to complete the remaining work. - Since Z completes \(\frac{1}{16}\) of the work in one day, the number of days Z needs to complete \(\frac{1}{4}\) of the work is: \[ \text{Days taken by Z} = \frac{\frac{1}{4}}{\frac{1}{16}} = \frac{1}{4} \times \frac{16}{1} = 4 \text{ days} \] ### Step 8: Calculate the total time taken to complete the work. - The total time taken is the sum of the days worked by X, Y, and Z: \[ \text{Total days} = 2 \text{ (days by X)} + 6 \text{ (days by Y)} + 4 \text{ (days by Z)} = 12 \text{ days} \] ### Final Answer: The total number of days required to complete the work is **12 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Question Bank - 20 (b)|15 Videos
  • SURDS

    S CHAND IIT JEE FOUNDATION|Exercise UNIT TEST -1 |15 Videos
  • TRIANGLES

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet|10 Videos

Similar Questions

Explore conceptually related problems

Karim can do (1)/(4) of a work in 5 days.How many days will he take to complete the work?

Acan do a work in 6 days and B in 9 days. How many days will both take together to complete the work?

27. 15 people completed a work in 7 days 10 How many days should people take to complete this work?

A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?

If A,B and C can respectively complete a piece of work in 20,24 and 36 days respectively .how many days will they take to complete the work, if they work together?

A's 2 days' work is equal to B's 3days' work. a complete work in 8 days then to complete the work B will take

X can do a piece of work in 40 days. He works it for 8 days and then Y finished it in 16 days How long will they together take to complete the work?

A can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?