A man completes 5/8 of a job in 10 days. At this rate, how many more days will it take him to finish the job?

A

5

B

6

C

7

D

`7(1)/(2)`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the reasoning outlined in the video transcript. ### Step 1: Understand the total work done The man completes \( \frac{5}{8} \) of a job in 10 days. We can assume the total work to be 1 unit. ### Step 2: Calculate the time taken to complete the whole job If \( \frac{5}{8} \) of the job takes 10 days, we can find out how long it would take to complete the entire job (1 unit) using the formula: \[ \text{Total time for 1 unit} = \text{Time taken for } \frac{5}{8} \text{ of the job} \times \frac{1 \text{ unit}}{\frac{5}{8} \text{ unit}} \] This simplifies to: \[ \text{Total time for 1 unit} = 10 \text{ days} \times \frac{8}{5} = 16 \text{ days} \] ### Step 3: Determine the remaining work The remaining work to be done is: \[ \text{Remaining work} = 1 - \frac{5}{8} = \frac{3}{8} \text{ of the job} \] ### Step 4: Calculate the time to finish the remaining work Now, we need to find out how many days it will take to complete the remaining \( \frac{3}{8} \) of the job. Since we know that the entire job takes 16 days, we can set up the equation: \[ \text{Time for } \frac{3}{8} \text{ of the job} = \frac{3}{8} \times 16 \text{ days} \] Calculating this gives: \[ \text{Time for } \frac{3}{8} \text{ of the job} = \frac{3 \times 16}{8} = \frac{48}{8} = 6 \text{ days} \] ### Conclusion Thus, the man will take **6 more days** to finish the job. ---
Doubtnut Promotions Banner Mobile Dark
|

Topper's Solved these Questions

  • RATIO,PROPORTION AND VARIATION

    DISHA PUBLICATION|Exercise Practice Exercises (Expert Level)|12 Videos
  • RATIO,PROPORTION AND VARIATION

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • RATIO,PROPORTION AND VARIATION

    DISHA PUBLICATION|Exercise Practice Exercises (Foundation Level)|57 Videos
  • QUADRATIC AND CUBIC EQUATIONS

    DISHA PUBLICATION|Exercise Test Yourself |15 Videos
  • SET THEORY

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos

Similar Questions

Explore conceptually related problems

5 men can complete a job in 8 days. How many days will it take if 12 men do the job?

Two men A and B started a job in which A was thrice as good as B and therefore took 60 days less than B to finish the job. How many days will they take to finish the job, if they start working together?

Knowledge Check

  • A man completes 4/9 of a job in 12 days. At this rate, how many more days will it take him to finish the job ?

    A
    15
    B
    10
    C
    9
    D
    `7(1)/(2)`
  • Shantanu completes 5//8 of a job in 20 days. At this rate, how many more days will he take to finish the job ?

    A
    6 days
    B
    18 days
    C
    5 days
    D
    12 days
  • A is thrice as good a workman as B and therefore is able to finish a job in 30 days less than B. How many days will they take to finish the job working together?

    A
    `10 (1)/(4)`
    B
    `11 (3)/(4)`
    C
    `11 (1)/(4)`
    D
    `11 (1)/(3)`
  • Similar Questions

    Explore conceptually related problems

    A person can do a job as fast as his two sons working together. If one son does the job in 6 days and the other in 12 days, how many days does it take the father to do the job ?

    6 men and 8 women can do a job in 10 days. In how many days can 3 men and 4 women finish the same job working together?

    22 men can complete a job in 16days. In how many days, will 32 men complete that job?

    Pramod has done (1)/(4) th of a job in 9 days, Saroj completes the rest of the job in 27 days. In how many days can they together finish the job?

    Jyothi can do (3)/(4) of a job in 12 days. Mala is twice as effticient as Joythi. In how many days will mala finish the job ?