2 men and 3 boys can do a work in 10 days, 3 men and 2 boys can do a work in 8 days . In how many days 2 men and 1 boy can do the same work ?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow these steps: ### Step 1: Define Variables Let the work done by one man in one day be \( m \) and the work done by one boy in one day be \( b \). ### Step 2: Set Up Equations From the first statement, "2 men and 3 boys can do a work in 10 days," we can express this as: \[ (2m + 3b) \times 10 = \text{Total Work} \quad \text{(Equation 1)} \] From the second statement, "3 men and 2 boys can do a work in 8 days," we can express this as: \[ (3m + 2b) \times 8 = \text{Total Work} \quad \text{(Equation 2)} \] ### Step 3: Equate Total Work Since both equations represent the same total work, we can set them equal to each other: \[ (2m + 3b) \times 10 = (3m + 2b) \times 8 \] ### Step 4: Expand and Simplify Expanding both sides gives: \[ 20m + 30b = 24m + 16b \] Now, rearranging the equation to isolate \( m \) and \( b \): \[ 20m - 24m + 30b - 16b = 0 \] \[ -4m + 14b = 0 \] \[ 4m = 14b \] \[ m = \frac{14}{4}b = \frac{7}{2}b \] ### Step 5: Substitute for Men in Terms of Boys Now, we can express the work done by 2 men in terms of boys: \[ 2m = 2 \times \frac{7}{2}b = 7b \] ### Step 6: Calculate Total Work for 2 Men and 1 Boy Now, we need to find out how much work 2 men and 1 boy can do in one day: \[ 2m + 1b = 7b + 1b = 8b \] ### Step 7: Find the Number of Days to Complete the Work We know from Equation 1 that the total work can be expressed as: \[ \text{Total Work} = (2m + 3b) \times 10 = (7b + 3b) \times 10 = 10b \times 10 = 100b \] Now, if 2 men and 1 boy can do \( 8b \) work in one day, the number of days \( x \) required to complete the total work is: \[ 8b \times x = 100b \] Dividing both sides by \( 8b \): \[ x = \frac{100b}{8b} = \frac{100}{8} = 12.5 \] ### Final Answer Thus, 2 men and 1 boy can complete the work in **12.5 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    MAHENDRA|Exercise EXERCISES|25 Videos
  • TEST-9 QUANTITATIVE APTITUDE

    MAHENDRA|Exercise MULTIPLE CHOICE QUESTIONS|50 Videos
MAHENDRA-TIME AND WORK -EXERCISES
  1. 2 men and 3 boys can do a work in 10 days, 3 men and 2 boys can do a w...

    Text Solution

    |

  2. If man A complete a work in 10 days & man B complete the same work in ...

    Text Solution

    |

  3. A B and C can complete a piece of work in 24, 6 and 12 days respective...

    Text Solution

    |

  4. A man can do a job in 15 days. His father takes 20 days and his son fi...

    Text Solution

    |

  5. A man can do a piece of work in 5 days, but with the help of his son h...

    Text Solution

    |

  6. A can lay railway track between two given stations in 16 days and B ca...

    Text Solution

    |

  7. A takes twice as much time as B and thrice as much time as C finish a ...

    Text Solution

    |

  8. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  9. Two workers A and B are engaged to do a piece of work. A working alone...

    Text Solution

    |

  10. P can complete a work in 12 days working 8 hours a day. Q can complete...

    Text Solution

    |

  11. A and B can do a work in 12 days, B and C in 15 days, C and A in 20 da...

    Text Solution

    |

  12. A and B can do a piece of work in 72 days, B and C can do it in 120 da...

    Text Solution

    |

  13. A and B can do a piece of work in 5 days, B and C can do it in 7 days ...

    Text Solution

    |

  14. A can do a piece of work in 4 hours: B and C can do it in 3 hours. A a...

    Text Solution

    |

  15. A can do a certain work in the same time in which B and C together can...

    Text Solution

    |

  16. A Works twice as fast as B. If B can complete a work in 12 days indepe...

    Text Solution

    |

  17. A is 30% more efficient than B. How much time will they, working toget...

    Text Solution

    |

  18. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  19. A can finish a work in 18 days and B can do the same work in 15 days. ...

    Text Solution

    |

  20. Ram and Mohan can complete a work in 15 days and 10 days respectively....

    Text Solution

    |

  21. A can finish a work in 24 days, B in 9 days and C in 12 days. B and C ...

    Text Solution

    |